FRONT PASSENGER AIRBAG ASSEMBLY (for Hatchback): Installation

WARNING: This page is about a different car, the 2008 Toyota Yaris. However, it is still accessible from the selected car via links, so may be relevant.
CAUTION: Some of these service operations affect the SRS airbag system. Read the precautionary notices concerning the SRS airbag system before servicing (See AIRBAG SYSTEM  ).
Fig 1: Removing Locking Button
G04830256Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
  1. INSTALL INSTRUMENT PANEL WIRE ASSEMBLY 
    1. Connect the airbag connector to install the instrument panel wire.
      NOTE:
      • Match the color of the connector of the instrument panel wire assembly with that of the connector of the front passenger assembly and install the airbag connector.
      • Lock the locking button securely.
      Fig 2: Installing Locking Button
      G04830257Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
  2. INSTALL FRONT PASSENGER AIRBAG ASSEMBLY 
    1. Engage the 10 hooks so that the connector side faces the outside of the vehicle and install the instrument panel passenger airbag.
    2. Install the wire harness onto the 2 claws of the instrument panel.
  3. INSTALL UPPER INSTRUMENT PANEL SUB-ASSEMBLY  (See INSTALLATION )
  4. INSTALL FRONT PILLAR GARNISH RH  (See INSTALLATION )
  5. INSTALL FRONT PILLAR GARNISH LH  (See INSTALLATION )
  6. INSTALL FRONT DOOR OPENING TRIM WEATHERSTRIP RH  (See INSTALLATION )
  7. INSTALL FRONT DOOR OPENING TRIM WEATHERSTRIP LH  (See INSTALLATION )
    Fig 3: Identifying Instrument Panel Passenger Airbag With Hooks
    G04830284Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
  8. INSTALL GLOVE COMPARTMENT DOOR ASSEMBLY  (See INSTALLATION )
  9. INSTALL NO. 1 SWITCH HOLE BASE  (See INSTALLATION )
  10. INSTALL COMBINATION METER ASSEMBLY  (See INSTALLATION )
  11. INSTALL INSTRUMENT CLUSTER FINISH PANEL  (See INSTALLATION )
  12. INSTALL INSTRUMENT PANEL FINISH PANEL END RH  (See INSTALLATION )
  13. INSTALL INSTRUMENT PANEL FINISH PANEL END LH  (See INSTALLATION )
  14. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL 

    Torque: 5.4 N*m (55 kgf*cm, 48 in.*lbf) 

  15. INSPECT SRS WARNING LIGHT 

    (See DIAGNOSIS SYSTEM  )