Skid Control Ecu: Installation
- INSTALL SKID CONTROL ECU
- Install the skid control ECU with the 2 nuts.
Torque: 5.0 N*m (51 kgf*cm, 44 in.*lbf)
- Connect the skid control ECU connectors.
- Install the skid control ECU with the 2 nuts.
- INSTALL INSTRUMENT PANEL INSERT SUB-ASSEMBLY LOWER LH (See INSTALLATION )
- INSTALL INSTRUMENT PANEL FINISH PANEL SUB-ASSEMBLY LOWER (See INSTALLATION )
- INSTALL COWL SIDE TRIM SUB-ASSEMBLY LH (See INSTALLATION )
- INSTALL FRONT DOOR SCUFF PLATE LH (See INSTALLATION )
- CONNECT CABLE TO NEGATIVE BATTERY TERMINAL
- INSPECT SRS WARNING LIGHT
(See DIAGNOSIS SYSTEM )
- PERFORM YAW RATE SENSOR ZERO POINT CALIBRATION
(See CALIBRATION )
- INSPECT VSC WARNING LIGHT
(See TEST MODE PROCEDURE )
- PERFORM LINEAR VALVE OFFSET LEARNING
- When he skid control ECU is replaced, perform linear valve offset learning. (See INITIALIZATION )
- PERFORM INITIALIZATION
Some systems need initialization after reconnecting the negative battery cable.
(See INITIALIZATION )