Installation [09/2015 - ]: Procedure
- INSTALL NO. 1 COMBINATION METER BRACKET
- Install the No. 1 combination meter bracket with the 2 bolts.
- INSTALL ACCESSORY METER ASSEMBLY
- INSTALL INSTRUMENT PANEL FINISH PANEL SUBASSEMBLY
Refer to PROCEDURE - Step 14
- INSTALL MULTI-MEDIA MODULE RECEIVER ASSEMBLY
Refer to PROCEDURE - Step 3
- INSTALL INSTRUMENT CLUSTER FINISH PANEL GARNISH ASSEMBLY
Refer to PROCEDURE - Step 19
- INSTALL LOWER NO. 2 INSTRUMENT PANEL FINISH PANEL
Refer to PROCEDURE - Step 5
- INSTALL LOWER NO. 1 INSTRUMENT PANEL FINISH PANEL
Refer to PROCEDURE - Step 4
- INSTALL UPPER CONSOLE PANEL SUBASSEMBLY
Refer to PROCEDURE - Step 6
- INSTALL UPPER INSTRUMENT CLUSTER FINISH PANEL
Refer to PROCEDURE - Step 7
- INSTALL UPPER REAR CONSOLE PANEL SUBASSEMBLY
Refer to PROCEDURE - Step 8
- INSTALL NO. 3 BOX PANEL
Refer to PROCEDURE - Step 9
- INSTALL SHIFT LEVER KNOB SUBASSEMBLY
Refer to PROCEDURE - Step 10
- INSTALL INSTRUMENT PANEL FINISH PANEL END RH
Refer to PROCEDURE - Step 12
- INSTALL INSTRUMENT PANEL FINISH PANEL END LH
Refer to PROCEDURE - Step 11
- CONNECT CABLE TO NEGATIVE BATTERY TERMINAL NOTE:
When disconnecting the cable, some systems need to be initialized after the cable is reconnected (Refer to INITIALIZATION [09/2015 - ] )
- INSTALL COWL TOP VENTILATOR LOUVER RH
Refer to PROCEDURE - Step 15