Removing and installing/replacing corrosion protection cover (S55 engine)
Necessary preliminary work:
- Remove SOUND INSULATION OF BULKHEAD UPPER SECTION, CENTER .
- Remove both charge-air ducts. Refer to REMOVING AND INSTALLING/REPLACING CHARGE AIR DUCT OF CYLINDER 4-6 and REMOVING AND INSTALLING/REPLACING THE CHARGE AIR DUCT FOR CYLINDERS 1-3 .
Removal:
Release clamps (2) from corrosion protection cover (1).
Pull corrosion protection cover (1) off upwards and remove.
Installation:
Install corrosion protection cover (1).
Corrosion protection cover (1) must engage in rubber mounts.
Fasten clamps (2) on corrosion protection cover.
Required follow-up work:
- Install both charge air ducts. Refer to REMOVING AND INSTALLING/REPLACING CHARGE AIR DUCT OF CYLINDER 4-6 and REMOVING AND INSTALLING/REPLACING THE CHARGE AIR DUCT FOR CYLINDERS 1-3 .
- Install SOUND INSULATION ON BULKHEAD UPPER PART, CENTER .