WASTEGATE Bypass Regulator Valve, Checking
Special tools and workshop equipment required
- Multimeter.
- Wiring diagram.
Test requirements
- The Motronic Engine Control Module (ECM) - J623- fuses OK.
- Battery voltage at least 12.5 volts.
- All electrical consumers such as, lights and rear window defroster, switched off.
- On vehicles with automatic transmission, selector lever in position "P" or "N".
- A/C switched off.
- Ground (GND) connections between engine/transmission/chassis OK.
- Ignition switched off.
Test procedure
-- Perform a preliminary check to verify the customers complaint. Refer to PRELIMINARY CHECK .
Start diagnosis
-- Remove the engine cover with air filter.
Checking internal resistance
-- Disconnect the Wastegate Bypass Regulator Valve -N75- electrical harness connector -1-.
-- Using a multimeter, check the Wastegate Bypass Regulator Valve -N75- terminals 1 to 2 for resistance.
Specified value: 20 to 30 Ω (at approx. 20° C)
If the specification was not obtained:
-- Replace the Wastegate Bypass Regulator Valve -N75-. Refer to Turbocharger Recirculation Valve -N249- AND Wastegate Bypass Regulator Valve -N75- .
If the specification is obtained:
Checking Voltage supply
-- Using a multimeter, check the Wastegate Bypass Regulator Valve -N75- electrical harness connector terminal 1 to Ground (GND) for voltage.
| Wastegate Bypass Regulator Valve -N75- electrical harness connector terminal | Measure to |
|---|---|
| 1 | Engine Ground (GND) |
-- Operate the starter briefly.
Specified value: battery voltage.
-- Switch the ignition off.
If the specification was not obtained:
-- Check the wiring for an open circuit, short circuit to each other, Battery (+), or Ground (GND).
-- Check the electrical harness connector for damage, corrosion, loose or broken terminals.
-- If necessary, repair the wiring connection.
If no malfunction is found in the wiring:
If the manufacturers test box is being used. Perform the following step.
-- Install the Test Box 105 Pin VAG 1598/42.
If the manufacturers test box is not being used. Perform the following step.
-- Remove the Motronic Engine Control Module (ECM) -J623-. Refer to ENGINE CONTROL MODULE, REMOVING AND INSTALLING .
-- Using a multimeter, check the Wastegate Bypass Regulator Valve -N75- electrical harness connector terminal 2 to the Motronic Engine Control Module (ECM) -J623- electrical harness connector T60 terminal 4 for resistance.
| Wastegate Bypass Regulator Valve -N75- electrical harness connector terminal | Motronic Engine Control Module (ECM) -J623- electrical connector T60 terminal or test box socket |
|---|---|
| 2 | 4 |
Specified value: 1.5 Ω max.
If the specification is not obtained:
-- Check the wiring for an open circuit, short circuit to each other, Battery (+), or Ground (GND).
-- Check the electrical harness connector for damage, corrosion, loose or broken terminals.
If no malfunction is found in wiring:
-- Erase the DTC memory. Refer to DIAGNOSTIC MODE 04 - ERASE DTC MEMORY .
-- Perform a road test to verify repair.
If the DTC does not return:
Repair complete, Generate readiness code. Refer to READINESS CODE .
-- End diagnosis.
If the DTC does return and no malfunction is detected in the wiring and the voltage supply was OK:
-- Replace the Motronic Engine Control Module (ECM) -J623-. Refer to ENGINE CONTROL MODULE, REMOVING AND INSTALLING .
Final procedures
After the repair work, the following work steps must be performed in the following sequence:
- Check the DTC memory. Refer to DIAGNOSTIC MODE 03 - READ DTC MEMORY .
- If necessary, erase the DTC memory. Refer to DIAGNOSTIC MODE 04 - ERASE DTC MEMORY .
- If the DTC memory was erased, generate readiness code. Refer to READINESS CODE .