Installation [07/2020 - ]: Procedure
- INSTALL COMBINATION METER ASSEMBLY
- Connect the 2 connectors.
- Engage the clamp.
- Engage the 2 pins and 2 clips.
- Install the combination meter assembly with the 4 screws.
Torque: 7.0 N*m (71 kgf*cm, 62 in.*lbf)
HINT:
Tighten the screws in the order shown in the illustration.
- INSTALL INSTRUMENT CLUSTER FINISH PANEL ASSEMBLY
- INSTALL UPPER CONSOLE COVER
Refer to PROCEDURE - Step 13
- INSTALL NO. 1 INSTRUMENT CLUSTER FINISH PANEL GARNISH
Refer to PROCEDURE - Step 22 [07/2020 - 10/2022] , or refer to PROCEDURE - Step 21 [10/2022 - ]
- INSTALL NO. 2 INSTRUMENT SIDE PANEL
Refer to PROCEDURE - Step 26 [07/2020 - 10/2022] , or refer to PROCEDURE - Step 25 [10/2022 - ]
- INSTALL FRONT DOOR OPENING TRIM WEATHERSTRIP LH
Refer to PROCEDURE - Step 1
- CONNECT CABLE TO NEGATIVE AUXILIARY BATTERY TERMINAL
Refer to PROCEDURE - Step 2
- INSTALL BATTERY HOLE COVER
Refer to PROCEDURE - Step 57 [07/2020 - 10/2022] , or refer to PROCEDURE - Step 57 [10/2022 - ]
- INSTALL REAR NO. 2 FLOOR BOARD
Refer to PROCEDURE - Step 4
- UPDATE ECU SECURITY KEY
Refer to UPDATE ECU SECURITY KEY [07/2020 - ]
- INITIALIZATION AFTER RECONNECTING AUXILIARY BATTERY TERMINAL
Refer to WORK PROCEDURE [07/2020 - 10/2022] , or refer to WORK PROCEDURE [10/2022 - ]
HINT:
When disconnecting and reconnecting the battery, there is an automatic learning function that completes learning when the respective system is used.
- CUSTOMIZE POWER TILT AND POWER TELESCOPIC STEERING COLUMN SYSTEM
Refer to PROCEDURE - Step 19 [07/2020 - 12/2021] , or refer to PROCEDURE - Step 19 [12/2021 - ]