Installation [12/2015 - 08/2016]: Procedure
WARNING: This page is about a different car, the 2016 Toyota Sienna. However, it is still accessible from the selected car via links, so may be relevant.
- INSTALL TRANSMISSION CONTROL CABLE ASSEMBLY
- Pass the transmission control cable from the cabin into the engine compartment.
- Install the transmission control cable with the 3 bolts.
Torque: 5.0 N*m (51 kgf*cm, 44 in.*lbf)
- Install a new clip onto the control cable bracket.TEXT IN ILLUSTRATION
*1 Claw A *2 Claw B *3 Transmission Control Cable - Install the transmission control cable onto the transmission control cable bracket.NOTE:
- Make sure that the claws A (*1) on the clip are securely fit into the bracket holes.
- Make sure that the cable is securely installed inside of the claws B (*2) of the clip.
- After installation, lightly jiggle the transmission control cable and make sure that it does not come loose from the transmission control cable bracket.
- Check that the park/neutral position switch is in the N position.
- Connect the transmission control cable onto the transmission control shaft lever with the nut.
Torque: 13 N*m (130 kgf*cm, 9 ft.*lbf)
- Rotate the transmission control cable nut counterclockwise approximately 270° and, while holding the nut in that position, press in the stopper until it makes 2 "click" sounds.TEXT IN ILLUSTRATION
*1 Stopper *2 Nut *a Turn *b Push - Push the lock piece up from the back side of the adjuster case while pinching the claws on the lock piece.TEXT IN ILLUSTRATION
*1 Adjuster Case *2 Claw *3 Lock Piece - Connect the cable outer of the transmission control cable onto the shift lever retainer, check that the position of the spring is the same as A shown in the illustration, and press in the stopper.
HINT:
If the stopper cannot be pressed in, slightly rotate the nut clockwise and then press in the stopper.
- Connect the transmission control cable end to the shift lever.TEXT IN ILLUSTRATION
*1 Lock Piece NOTE:Check that the lock piece is pulled up.
- INSTALL FRONT NO. 1 FLOOR HEAT INSULATOR
- INSTALL EXHAUST MANIFOLD ASSEMBLY RH
(Refer to INSTALLATION [12/2015 - 08/2016] )
- INSTALL AIR CLEANER ASSEMBLY
Refer to PROCEDURE - Step 4
- INSTALL BATTERY
Refer to PROCEDURE - Step 61
- INSTALL AIR CLEANER INLET ASSEMBLY
Refer to PROCEDURE - Step 62
- INSTALL FRONT AIR CONDITIONING UNIT
(Refer to INSTALLATION [12/2015 - 08/2016] )
- CONNECT CABLE TO NEGATIVE BATTERY TERMINAL
Torque: 5.4 N*m (55 kgf*cm, 48 in.*lbf)
- When disconnecting the cable, some systems need to be initialized after the cable is reconnected (Refer to INITIALIZATION [12/2015 - 08/2016] ).
- INSPECT SHIFT LEVER POSITION
See step 1