Installation [06/2017 - ]: Procedure
WARNING: This page is about a different variant/trim than selected.
- INSTALL GENERATOR ASSEMBLY
- Install the generator assembly with the 2 bolts.
Torque: 43 N*m (438 kgf*cm, 32 ft.*lbf)
- Install the generator assembly bracket with the 2 bolts in the order shown in the illustration.
Torque: 20 N*m (204 kgf*cm, 15 ft.*lbf)
- Install the wire harness clamp bracket with the 2 bolts.
Torque: 10 N*m (102 kgf*cm, 7 ft.*lbf)
- Engage the 3 wire harness clamps.
- Connect the camshaft timing oil control solenoid assembly connector.
- Connect the compressor assembly with magnetic clutch connector.
- Connect the generator assembly connector.
- Connect the wire harness to terminal B with the nut.
Torque: 9.8 N*m (100 kgf*cm, 87 in.*lbf)
- Close the terminal cap.
- Install the generator assembly with the 2 bolts.
- INSTALL V-RIBBED BELT
Refer to INSTALLATION [06/2017 - ]
- INSTALL V-BANK COVER SUB-ASSEMBLY
Refer to PROCEDURE - Step 46 [06/2017 - 10/2020] , or refer to PROCEDURE - Step 46 [10/2020 - ]
- INSTALL RADIATOR ASSEMBLY
Refer to INSTALLATION [06/2017 - ]
- CONNECT CABLE TO NEGATIVE BATTERY TERMINAL NOTE:
When disconnecting the cable, some systems need to be initialized after the cable is reconnected.
Refer to INITIALIZATION [06/2017 - 08/2018] , or refer to INITIALIZATION [08/2018 - 09/2019] , or refer to INITIALIZATION [09/2019 - 03/2020] , or refer to INITIALIZATION [03/2020 - 10/2020] , or refer to INITIALIZATION [10/2020 - 08/2022] , or refer to INITIALIZATION [08/2022 - ]