LEMON Manuals: Even more car manuals for everyone
Home >> Toyota >> 2017 >> Prius Three >> Repair and Diagnosis >> Transmission >> Automatic Trans >> Hybrid Transaxle - Service Information >> Shift Lever >> Installation [11/2015 -] >> Procedure

Installation [11/2015 -]: Procedure

  1. INSTALL SHIFT LOCK CONTROL UNIT ASSEMBLY 
    1. Connect the shift lock control unit assembly connector.
    2. Install the shift lock control unit assembly to the No. 1 instrument panel brace sub-assembly and No. 2 instrument panel brace sub-assembly with the 3 nuts.

      Torque: 12 N.m (122 kgf.cm, 9 ft./lbf) 

    3. Engage the clamp.
  2. INSTALL NO. 2 LOWER INSTRUMENT PANEL FINISH PANEL 

    Refer to PROCEDURE - Step 6 [11/2015 - 11/2017] , or refer to PROCEDURE - Step 6 [11/2017 - 08/2019] , or refer to PROCEDURE - Step 6 [08/2019 -]

  3. INSTALL SHIFT LEVER HOLE COVER 

    Refer to PROCEDURE - Step 7 [11/2015 - 11/2017] , or refer to PROCEDURE - Step 7 [11/2017 - 08/2019] , or refer to PROCEDURE - Step 7 [08/2019 -]

  4. INSTALL LOWER CENTER INSTRUMENT CLUSTER FINISH PANEL SUB-ASSEMBLY 

    Refer to PROCEDURE - Step 8 [11/2015 - 11/2017] , or refer to PROCEDURE - Step 8 [11/2017 - 08/2019] , or refer to PROCEDURE - Step 8 [08/2019 -]

  5. INSTALL LOWER NO. 1 INSTRUMENT PANEL AIRBAG ASSEMBLY 

    Refer to PROCEDURE - Step 1

  6. INSTALL LOWER INSTRUMENT PANEL FINISH PANEL ASSEMBLY 

    Refer to PROCEDURE - Step 20 [11/2015 - 11/2017] , or refer to PROCEDURE - Step 22 [11/2017 - 08/2019] , or refer to PROCEDURE - Step 21 [08/2019 -]

  7. CONNECT HOOD LOCK CONTROL LEVER SUB-ASSEMBLY 

    Refer to PROCEDURE - Step 21 [11/2015 - 11/2017] , or refer to PROCEDURE - Step 23 [11/2017 - 08/2019] , or refer to PROCEDURE - Step 22 [08/2019 -]

  8. INSTALL NO. 1 INSTRUMENT PANEL UNDER COVER SUB-ASSEMBLY 

    Refer to PROCEDURE - Step 22 [11/2015 - 11/2017] , or refer to PROCEDURE - Step 24 [11/2017 - 08/2019] , or refer to PROCEDURE - Step 23 [08/2019 -]

  9. INSTALL COWL SIDE TRIM BOARD LH 

    Refer to PROCEDURE - Step 50 [11/2015 - 12/2018] , or refer to PROCEDURE - Step 46 [12/2018 - 07/2020] , or refer to PROCEDURE - Step 46 [07/2020 -]

  10. INSTALL FRONT DOOR SCUFF PLATE LH 

    Refer to PROCEDURE - Step 51 [11/2015 - 12/2018] , or refer to PROCEDURE - Step 47 [12/2018 - 07/2020] , or refer to PROCEDURE - Step 47 [07/2020 -]

  11. INSTALL INSTRUMENT CLUSTER FINISH PANEL GARNISH ASSEMBLY 

    Refer to PROCEDURE - Step 25 [11/2015 - 11/2017] , or refer to PROCEDURE - Step 27 [11/2017 - 08/2019] , or refer to PROCEDURE - Step 26 [08/2019 -]

  12. INSTALL INSTRUMENT PANEL FINISH PANEL END LH 

    Refer to PROCEDURE - Step 26 [11/2015 - 11/2017] , or refer to PROCEDURE - Step 28 [11/2017 - 08/2019] , or refer to PROCEDURE - Step 27 [08/2019 -]

  13. INSTALL REAR CONSOLE BOX ASSEMBLY 

    Refer to INSTALLATION [11/2015 - 12/2018] , or refer to INSTALLATION [12/2018 -]

  14. CONNECT CABLE TO NEGATIVE AUXILIARY BATTERY TERMINAL 
    NOTE:

    When disconnecting the cable, some systems need to be initialized after the cable is reconnected.

    Refer to INITIALIZATION [11/2015 - 11/2017] , or refer to INITIALIZATION [11/2017 - 12/2018] , or refer to INITIALIZATION [12/2018 - 08/2019] , or refer to INITIALIZATION [08/2019 - 07/2020] , or refer to INITIALIZATION [07/2020 -]

  15. INSPECT SHIFT LEVER 
    1. Turn the power switch on (READY).
    2. Check that all shift positions can be selected by moving the shift lever.

      HINT: 

      After the shift lock control unit assembly is replaced with a new one, perform the above operation. If this operation is not performed, moving the shift lever may not initially select shift positions.