Inspection Procedure
WARNING: This page is about a different variant/trim than selected.
- INSPECT TRANSMISSION WIRE (ST)
- Disconnect the transmission wire connector from the transaxle.
- Measure the resistance according to the value(s) in the table below.
Standard resistance
TESTER CONNECTION SPECIFIED CONDITION CHARTTester Connection Condition Specified Condition 2 - Body ground 20°C (68°F) 11 to 15 Ω NG: Go to step 3
Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
OK: Go to next step
- CHECK HARNESS AND CONNECTOR (TRANSMISSION WIRE - ECM)
- Connect the transmission wire connector to the transaxle.
- Disconnect the ECM connectors.
- Measure the resistance according to the value(s) in the table below.
Standard resistance
TESTER CONNECTION SPECIFIED CONDITION CHARTTester Connection Condition Specified Condition B31-80 (ST) - Body ground 20°C (68°F) 11 to 15 Ω NG: REPAIR OR REPLACE HARNESS OR CONNECTOR
OK: REPLACE ECM (for 2ZR-FE) (See REMOVAL )
- INSPECT SHIFT SOLENOID VALVE ST
- Remove the shift solenoid valve ST.
- Measure the resistance according to the value(s) in the table below.
Standard resistance
TESTER CONNECTION SPECIFIED CONDITION CHARTTester Connection Condition Specified Condition Solenoid Connector (ST) - Solenoid Body (ST) 20°C (68°F) 11 to 15 Ω - Connect the positive (+) lead to the terminal of the solenoid connector, and the negative (-) lead to the solenoid body.
OK:
The solenoid makes an operating sound.
NG: REPLACE SHIFT SOLENOID VALVE ST (See DISASSEMBLY )
OK: REPAIR OR REPLACE TRANSMISSION WIRE (See REMOVAL )