Subsequent Work
WARNING: This page is about a different car, the 2024 Porsche 911, 2023 Porsche 911, and 2022 Porsche 911. However, it is still accessible from the selected car via links, so may be relevant.
Information
- When the work is complete, check that all aids and foreign objects (e.g. cloths, tools) are removed from the engine compartment.
- Install the oil separator.
- Install oil cooler.
174019 REMOVING AND INSTALLING OIL COOLER (OIL-WATER HEAT EXCHANGER)
- Fit air-conditioning compressor and secure with holders.
> WM, 873419 REMOVING AND INSTALLING AIR-CONDITIONING COMPRESSOR
- Install intake-air distributor pipe on cylinder bank 4-6.
- Install the centre intake-air distributor.
244619 REMOVING AND INSTALLING (CENTRE) INTAKE-AIR DISTRIBUTOR
- Raise the engine.
Slowly raise the engine with the jack and secure it.
- Check the coolant level and top up if necessary.
- Install air cleaner housing.
- Fill in engine oil.
- Let the engine run until warm and visually check for leaks.
- Install rear underbody panelling.
- Make sure there are no tools, foreign objects or aids in the engine compartment!
- Complete the vehicle.