Assembling the dashboard: Notes

WARNING: This page does not describe the selected car, but rather 7 other vehicles, including the 2005 Porsche 911, 2004 Porsche 911, 2003 Porsche 911, 2002 Porsche 911, and 2001 Porsche 911. However, it is still accessible from the selected car via links, so may be relevant.
Fig 1: Assembling Dashboard (Steps 1-5) (As Of MY 1997)
G03105999Courtesy of PORSCHE OF NORTH AMERICA, INC.
DASHBOARD ASSEMBLING PROCEDURE (STEPS 1-5) (AS OF MY 1997)

No. Procedure Instructions
  Installing the regulator for wiping interval  
  Installing the cigarette lighter  
1 Installing the inside retaining bracket and the central vent Position the inside retaining bracket -57-1-56-55-54-  . See Fig 1 .
2 Installing the PCM retaining bracket Insert the retaining bracket -52-53-  . See Fig 1 .
3 Installing the PCM -50-  . See Fig 1 . Connect the electrical plug connection -51-  . See Fig 1 .
    Refer to REMOVING AND INSTALLING DISPLAY AND OPERATOR CONTROL UNIT (PCM) .
4 Installing the electrical air-conditioning and heating regulator variant -47-48-  . See Fig 1 . Refer to REMOVING AND INSTALLING HEATING/AIR-CONDITIONING CONTROL and RADIO - 911 CARRERA (996) .
5 Installing the switch covers Plug in the electrical plug connections. (Observe the colour designation of the wiring harness switches). -4-45 and 46-  . See Fig 1 .
    Check the clips -4-45 and 46-  . See Fig 1 .
Fig 2: Assembling Dashboard (Steps 6-10) (As Of MY 1997)
G03106000Courtesy of PORSCHE OF NORTH AMERICA, INC.
DASHBOARD ASSEMBLING PROCEDURE (STEPS 6-10) (AS OF MY 1997)

No. Procedure Instructions
6 Installing the steering column cover Position the steering column cover -44-43-  . See Fig 2 .
7 Installing the steering column switch Connect the electrical plug connection of the steering column switch -42-41-38-37-  . See Fig 2 .
    Refer to REMOVING AND INSTALLING THE CONTACT UNIT .
8 Installing the steering column switch cover Position the steering column switch cover at the top and bottom or laterally -33, 36, 35-32-36-33-  . See Fig 2 .
9 Installing left side vents and main light switch Connect the electrical plug connection-30-31-27-29-27-26-3.5 Nm (2.5 ftlb.)--21-25-28-  . See Fig 2 .
10 Installing the right side vents and the temperature sensor Engage the temperature sensor -24-1-22-1-21-20, 20A  . See Fig 2 .
Fig 3: Assembling Dashboard (Steps 11-15) (As Of MY 1997)
G03106001Courtesy of PORSCHE OF NORTH AMERICA, INC.
DASHBOARD ASSEMBLING PROCEDURE (STEPS 11-15) (AS OF MY 1997)

No. Procedure Instructions
11 Connecting instrument cluster electrical plug connection Plug in the electrical plug connection of the instrument mount. After inserting the plug connection -18-direction of the arrow-  . See Fig 3 .
12 Installing instrument mount Install the hazard warning light switch -13-14-4-16-12-17-  . See Fig 3 .
13 Installing the loudspeaker Connect electrical plug connection -11-9-  . See Fig 3 .
14 Installing the alarm readiness unit Connect the plug connection. Secure the alarm readiness unit-8-7-  . See Fig 3 .
15 Installing the alarm readiness cover and the defroster cover Clip the defroster covers on the left and right -5, 6-4-3-8-4-  . See Fig 3 .