Install the high-pressure line between the high-pressure rail and the high-pressure pump
- Feed in high pressure line (1) and position.
- Hand-tighten the union nut (2) on the rail (3).
- Hand-tighten the union nut (4) on the high pressure pump (5).
- Tighten union nut (2) on rail (3).TIGHTENING TORQUES SPECIFICATION
Pressure line between rail and high pressure pump M14 Tightening torque 33Nm - Tighten the union nut (4) on the high pressure pump (5).TIGHTENING TORQUES SPECIFICATION
Pressure line between rail and high pressure pump M14 Tightening torque 33Nm - Insert and install the sound insulation (2).
- Connect and lock the connector (1).
- Make sure the connector (1) engages audibly.
Follow-up work
- Refer to INSTALLING THE IGNITION COILS .
- Refer to INSTALLING ACOUSTIC COVER .
- Refer to INSTALLING THE UPPER BULKHEAD COVER PANEL .
- Refer to INSTALLING THE STRUT BRACE .
- Refer to CONNECTING ALL BATTERY GROUND LEADS .
- Refer to INSTALLING FRONT WINDSHIELD PANEL COVER .
- Refer to INSTALLING THE FRONT HOOD SEAL AT THE REAR .