13 51 065 Removing and installing/replacing left high pressure pump (N63 hybrid)
- DE-ENERGIZE THE HIGH-VOLTAGE SYSTEM
- Observe SAFETY INSTRUCTIONS for handling with hybrid vehicles
Disconnect BATTERY NEGATIVE TERMINAL (risk of fire due to short-circuiting on removal).
Electric fuel pump starts up automatically when door is opened!
Carry out installation work on fuel system only with coolant temperature below 40 °C.
Fuel can emerge spontaneously at high velocity when the high-pressure line is released!
Introduced contaminants can cause malfunctions in the system!
- Do not allow any dirt particles or foreign bodies to get into the system.
- Remove all traces of dirt before removing pipes or individual components.
- Use only fluff-free cloths.
- Seal all fuel system openings with protective caps or plugs.
The resistance of the silicone material is reduced significantly by contact with fuel, which may cause the ignition coil to fail!
Cover ignition coil with suitable means.
Necessary preliminary tasks:
- Remove FUEL FEED LINE
- Remove HIGH-PRESSURE LINE from left high-pressure pump to rail.
Recycling:
Fuel escapes when fuel lines are detached.
Catch and dispose of escaping fuel.
Observe country-specific waste-disposal regulations.
High-pressure pump can be pretensioned by camshaft cams!
Slightly slacken screws (1) of high pressure pump (2). If the high pressure pump is forced out, the engine will have to be turned to bring the camshafts to a different position.
Otherwise it will not be possible to install the high-pressure pump! Release screws (1).
Replace screws. Screws are coated with a screw locking agent.
The pump plunger can fall out when the high-pressure pump (2) is pulled out! Detach high-pressure pump (2) and remove.
Engine oil can emerge when pulling off the pump; have cloths ready.
Installation note:
Before installing the high pressure pump, the cam of the high pressure pump drive must be turned to BDC . To do this, twist the engine if necessary in the direction of engine rotation to the central bolt of the crankshaft.
Adhere to tightening/torque sequence.
Lay depth gauge (1) flat on high pressure pump flange.
Turn engine at central bolt in direction of engine rotation until the depth gauge shows that the camshaft has reached the BDC position .
Release screws (1).
Replace screws (1). Screws (1) are coated with sealant.
Detach high-pressure pump (2) and remove.
Engine oil can escape when pump is detached; have a cleaning cloth ready.
Installation note:
Before installing the high pressure pump, the cam of the high pressure pump drive must be turned to bottom dead center. To do this, twist the engine if necessary in the direction of engine rotation to the central bolt of the crankshaft.
Adhere to tightening/torque sequence.
Installation note:
Replace sealing ring (1).
Clean contact surfaces.
Install high pressure pump (2).
Replace screws (1). Screws (1) are coated with sealing compound.
Installation note:
Provisionally fasten screws (1) on high pressure pump (2) and tighten alternately in 90° increments until final tightening, otherwise the piston may break as a result of tilting!
Tightening torque 13 51 1AZ .
Assemble engine.
Check fuel system for leaks.
Check function of DME.