Installation [03/2017 - ]: Procedure

WARNING: This page does not describe the selected car, but rather 7 other vehicles, including the 2024 Lexus LC 500, 2023 Lexus LC 500, 2022 Lexus LC 500, 2021 Lexus LC 500, and 2020 Lexus LC 500. However, it is still accessible from the selected car via links, so may be relevant.
  1. INSTALL METER HOOD SPACER 
    1. Attach the claws to install the meter hood spacer.
      GTY810073Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
  2. INSTALL COMBINATION METER ASSEMBLY 
    1. Temporarily install the combination meter assembly in the direction indicated by the arrow in the illustration.
      GTY811635Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
      Install in this Direction
    2. Connect the 2 connectors and attach the wire harness clamps.
      GTY802653Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
    3. Attach the guides and claws in the direction indicated by the arrow in the illustration.
      GTY792743Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
      Install in this Direction
    4. Install the combination meter assembly with the 4 screws.
      GTY802669Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
  3. INSTALL METER HOOD SUB-ASSEMBLY 

    Refer to PROCEDURE - Step 38 [03/2017 - 06/2019] , or refer to PROCEDURE - Step 38 [06/2019 - 04/2020] , or refer to PROCEDURE - Step 38 [04/2020 - 05/2023] , or refer to INSTALLATION [05/2023 - ]

  4. INSTALL CENTER UPPER INSTRUMENT CLUSTER FINISH PANEL 

    Refer to PROCEDURE - Step 39 [03/2017 - 06/2019] , or refer to PROCEDURE - Step 39 [06/2019 - 04/2020] , or refer to PROCEDURE - Step 39 [04/2020 - 05/2023] , or refer to INSTALLATION [05/2023 - ]

  5. CUSTOMIZE POWER TILT AND POWER TELESCOPIC STEERING COLUMN SYSTEM 

    Refer to PROCEDURE - Step 18 [03/2017 - 09/2018] , or refer to PROCEDURE - Step 18 [09/2018 - 05/2023] , or refer to INSTALLATION [05/2023 - 09/2023] , or refer to INSTALLATION [09/2023 - ]