Installation [10/2015 - 03/2018]: Procedure
- INSTALL COMBINATION METER ASSEMBLY
- Connect each connector.
- Engage the clamp.
- Install the combination meter assembly with the 4 screws.
- INSTALL INSTRUMENT CLUSTER FINISH PANEL SUB-ASSEMBLY
- INSTALL LOWER INSTRUMENT FINISH PANEL SUB
Refer to PROCEDURE - Step 32 [10/2015 - 12/2017] Refer to PROCEDURE - Step 32 [12/2017 - 03/2018]
- INSTALL INSTRUMENT CLUSTER FINISH PANEL ORNAMENT
Refer to PROCEDURE - Step 6 [10/2015 - 12/2017] Refer to PROCEDURE - Step 5 [12/2017 - 08/2019]
- INSTALL LOWER NO. 1 INSTRUMENT PANEL FINISH PANEL
Refer to PROCEDURE - Step 8 [10/2015 - 12/2017] Refer to PROCEDURE - Step 7 [12/2017 - 08/2019]
- INSTALL LOWER NO. 2 INSTRUMENT PANEL FINISH PANEL
Refer to PROCEDURE - Step 9 [10/2015 - 12/2017] Refer to PROCEDURE - Step 8 [12/2017 - 08/2019]
- INSTALL LOWER INSTRUMENT PANEL FINISH PANEL SUB-ASSEMBLY
Refer to PROCEDURE - Step 33 [10/2015 - 12/2017] Refer to PROCEDURE - Step 33 [12/2017 - 03/2018]
- CONNECT HOOD LOCK CONTROL LEVER SUB-ASSEMBLY
Refer to PROCEDURE - Step 34 [10/2015 - 12/2017] Refer to PROCEDURE - Step 34 [12/2017 - 03/2018]
- INSTALL NO. 1 INSTRUMENT PANEL UNDER COVER SUB-ASSEMBLY
Refer to PROCEDURE - Step 35 [10/2015 - 12/2017] Refer to PROCEDURE - Step 35 [12/2017 - 03/2018]
- INSTALL COWL SIDE TRIM BOARD LH
Refer to PROCEDURE - Step 2
- INSTALL FRONT DOOR SCUFF PLATE LH
Refer to PROCEDURE - Step 43 [10/2015 - 12/2017] Refer to PROCEDURE - Step 42 [12/2017 - ]
- INSTALL INSTRUMENT PANEL GARNISH LH
Refer to PROCEDURE - Step 38 [10/2015 - 12/2017] Refer to PROCEDURE - Step 38 [12/2017 - 03/2018]
- CONNECT CABLE TO NEGATIVE AUXILIARY BATTERY TERMINAL
Refer to PROCEDURE - Step 2
- CUSTOMIZE POWER TILT AND POWER TELESCOPIC STEERING COLUMN SYSTEM
Refer to CUSTOMIZE PARAMETERS [10/2015 - ]
- INSTALL REAR DECK FLOOR BOX
Refer to PROCEDURE - Step 54 [10/2015 - 12/2017] Refer to PROCEDURE - Step 53 [12/2017 - ]
- INSTALL DECK BOARD ASSEMBLY
Refer to PROCEDURE - Step 56 [10/2015 - 12/2017] Refer to PROCEDURE - Step 55 [12/2017 - ]