Inspection Procedure
WARNING: This page is about a different car, the 2008 Lexus IS F. However, it is still accessible from the selected car via links, so may be relevant.
NOTE:
When the seat belt control ECU is replaced with a new one, Initialization must be performed (See INITIALIZATION
).
- INSPECT FRONT SEAT OUTER BELT ASSEMBLY RH
- Disconnect the P8 connector of the front seat outer belt assembly RH.
- Measure the voltage according to the value (s) in the table below.
Standard Voltage
STANDARD VOLTAGE SPECIFICATIONTester Connection Switch Condition Specified Condition P8-1 - Body ground Engine switch on (IG) Below 1 V P8-2 - Body ground Engine switch on (IG) Below 1 V
NG: REPLACE FRONT SEAT OUTER BELT ASSEMBLY RH (See REMOVAL )
OK: Go to next Step
- CHECK HARNESS AND CONNECTOR (FRONT SEAT OUTER BELT ASSEMBLY RH - SEAT BELT CONTROL ECU)
- Disconnect the cable from the negative (-) battery terminalCAUTION: Wait at least 90 seconds after disconnecting the cable from the negative (-) battery terminal to disable the SRS system.NOTE: When disconnecting the cable, some systems need to be initialized after the cable is reconnected (See INITIALIZATION ).
- Disconnect the Q38 connector of the seat belt control ECU
- Connect the cable to the negative battery terminal
- Measure the voltage according to the value (s) in the table below
Standard Voltage
STANDARD VOLTAGE SPECIFICATIONTester Connection Switch Condition Specified Condition P8-1 - Body ground Engine switch on (IG) Below 1 V P8-2 - Body ground Engine switch on (IG) Below 1 V
NG: REPAIR OR REPLACE HARNESS OR CONNECTOR
OK: REPLACE SEAT BELT CONTROL ECU (See SEAT BELT CONTROL ECU )
- Disconnect the cable from the negative (-) battery terminal