Transfer Case Input Shaft Seal LH: Installation

WARNING: This page is about a different car, the 2018 Ford Edge. However, it is still accessible from the selected car via links, so may be relevant.
  1. Using the special tools, install a new LH input shaft seal. Use Special Service Tool: 308-878 Installer, Input Seal., 205-153 (T80T-4000-W) Handle.
    GFD281813Courtesy of FORD MOTOR COMPANY
  2. Install the input shaft.
    GFD281811Courtesy of FORD MOTOR COMPANY
  3. Install a new PTU cover O-ring seal.
    GFD281807Courtesy of FORD MOTOR COMPANY
  4. Install the PTU cover and the new PTU cover bolts.

    Torque

    :Stage 1: 115 lb.in (13 Nm) Stage 2: 45 deg.

    GFD281808Courtesy of FORD MOTOR COMPANY
    NOTE: Hand start bolts for the first three threads to ensure cross-threading does not occur.
  5. Install the PTU/transfer case. Refer to: Transfer Case .