Installation Procedure
WARNING: This page is about a different car, the 2017 Chevrolet Spark. However, it is still accessible from the selected car via links, so may be relevant.
- Coat the shift control housing with recommended Shift Control Housing Sealant -THREE BOND 1215 or LOCTITE 5702.
- Install the shift control housing assembly (2) to the transmission.
- Install the 4 shift control housing bolts (1) to the shift control housing and tighten to 23 N.m (17 lb ft).CAUTION: Refer to Fastener Caution .
- Install the shift interlock washer (2) and bolt (1) and tighten to 23 N.m (17 lb ft).
- Install the shift lever and selector lever cable to the shift control housing. Refer to Manual Transmission Shift Lever and Selector Lever Cable Replacement .
- Install the radiator surge tank. Refer to Radiator Surge Tank Replacement .
- Install the battery tray. Refer to Battery Tray Replacement (without Engine Block Heater)Battery Tray Replacement (with Engine Block Heater) .