Removal Procedure
- Recover the refrigerant. Refer to Refrigerant Recovery and Recharging .
- Drain the cooling system. Refer to Cooling System Draining and Filling (GE-47716 Fill) and Cooling System Draining and Filling (Static Fill) .
- Remove instrument panel tie bar. Refer to Instrument Panel Tie Bar Replacement .
- Remove instrument panel tie bar (2).
- Remove 4 instrument panel tie bar bolts (3, 4).
- Remove 2 instrument panel tie bar nuts (1).
- Remove air conditioning module wiring harness (1).
- Disconnect electrical connectors.
- Remove heater core. Refer to Heater Core Replacement .
- Remove blower motor. Refer to Blower Motor Replacement .
- Remove heater and blower and air conditioning control module. Refer to Heater and Blower and Air Conditioning Control Module Replacement or Heater and Blower and Air Conditioning Control Module Replacement .
- Remove heater and air conditioning evaporator case (2) from heater and blower and air conditioning control module (1).
- Remove 10 heater and air conditioning evaporator case bolts (3).