Test Description
The number(s) below refer to the step number(s) on the diagnostic table.
- 5: Test the entire ignition voltage circuit, which includes the ignition switch and the fuses.
- 6: Test the entire crank voltage circuit, which includes the ignition switch and the fuse.
- 7: Test the entire ignition 1 voltage circuit, which includes the ignition switch and the fuse.
DTC B0608
| Step | Action | Value(s) | Yes | No |
|---|---|---|---|---|
| Schematic Reference: Instrument Cluster Schematics | ||||
| 1 | Did you perform the Instrument Cluster Diagnostic System Check? | - | Go to Step 2 | Go to Diagnostic System Check - Instrument Cluster |
| 2 |
|
- | Go to Step 3 | Go to Step 5 |
| 3 |
|
- | Go to Step 4 | Go to Step 6 |
| 4 |
|
- | Go to Testing for Intermittent Conditions and Poor Connections in Wiring Systems | Go to Step 7 |
| 5 | Test the inactive ignition voltage circuit for an open, a high resistance, or a short to ground. Refer to Circuit Testing
and Wiring Repairs
in Wiring Systems. Did you find and correct the condition? |
- | Go to Step 10 | Go to Step 8 |
| 6 | Test the crank voltage circuit of the IPC for a short to voltage. Refer to Circuit Testing
and Wiring Repairs
in Wiring Systems. Did you find and correct the condition? |
- | Go to Step 10 | Go to Step 8 |
| 7 | Test the ignition 1 voltage circuit for a short to voltage. Refer to Circuit Testing
and Wiring Repairs
in Wiring Systems. Did you find and correct the condition? |
- | Go to Step 10 | Go to Step 8 |
| 8 | Inspect for poor connections at the harness connector of the IPC. Refer to Testing for Intermittent Conditions and Poor Connections
and Connector Repairs
in Wiring Systems. Did you find and correct the condition? |
- | Go to Step 10 | Go to Step 9 |
| 9 | Replace the IPC. Refer to Instrument Panel Cluster (IPC) Replacement . Did you complete the replacement? |
- | Go to Step 10 | - |
| 10 |
|
- | Go to Step 2 | System OK |