Installing rail on bank 2
- Position high pressure rail.
- Manually tighten the screws (1) as far as they will go.
- Manually tighten the screws (1) as far as they will go.
- Tighten nut (2) on the high pressure pump with the special tool 0 491 277 (13 5 020)
.TIGHTENING TORQUE SPECIFICATION
Fuel supply line/rail to high pressure pump Nut tightening torque 30 Nm - Tighten nuts (1) on the injectors with the special tool 0 495 908 (37 1 150)
.TIGHTENING TORQUE SPECIFICATION
High-pressure rail to injectors Nuts Tightening torque 25 Nm - Position high pressure rail.
- Tighten down screws (1).TIGHTENING TORQUE SPECIFICATION
Rail to cylinder head cover M6x25 screw Tightening torque 10 Nm - Tighten down screws (1).TIGHTENING TORQUE SPECIFICATION
Hold-down device to cylinder head cover screw Tightening torque 13 Nm - Connect connectors (1) and lock.
- Position ground cable (2).
- Tighten nuts (1).
- Connect connectors (1) and lock.
Follow-up work
- Refer to INSTALLING THE IGNITION COILS OF CYLINDER BANK 2 .
- Refer to INSTALLING THE LEFT INTAKE SILENCER BRACKET .
- Refer to INSTALLING LEFT INTAKE SILENCER HOUSING .
- Refer to INSTALLING ACOUSTIC COVER .
- Refer to ACTIVATING VEHICLE-SPECIFIC HIGH-VOLTAGE OR LOW-VOLTAGE VEHICLE ELECTRICAL SYSTEM .