11 00 590 Replacement power plant (N54)
WARNING: This page is about a different car, the 2010 BMW X6, 2009 BMW X6, and 2008 BMW X6. However, it is still accessible from the selected car via links, so may be relevant.
Necessary preliminary tasks:
- Remove and install engine .
- Mount engine on assembly stand .
- If necessary, remove foreign bodies from turbocharger group.
- Check all assemblies and convert to replacement power plant.
Remove transportation locks (1).
NOTE:
Catch escaping engine oil with a suitable cloth (2).
Transportation locks (1) are no longer needed.
Modify screw plugs (1) from old power plant.
Insert screw plugs (1).
Tightening torque: 11 42 11AZ , see OIL FILTER AND LINES
Secure oil cooler lines with mounting bar (2).
Assemble engine.