26 11 000 Removing and installing propeller shaft (cardan universal joint) completely

Necessary preliminary tasks: 

IMPORTANT:

To avoid buzzing sound after refitting the propeller shaft:

  1. The flexible disc connection (1) on the front at the propeller shaft must be marked in one plane with the flexible disc (2) and the three-bolt flange (3) before removal.
  2. During installation the three-bolt flange (3) must be forced back together again with the flexible disc (2) in the same position.
  3. Replace ZNS bolts and self-locking nuts.

Fig 1: Refitting Propeller Shaft
G00524370Courtesy of BMW OF NORTH AMERICA, INC.

Release screws.

Installation: 

Tighten down screws/bolts to specified torque.

Secure special tool angle of rotation 00 9 120 with magnet 00 9 130 to underbody and continue bolting according to angle of rotation, for tightening torque refer to 26 11 1AZ in 26 11 PROPELLER SHAFT COMPLETE (1AZ-3AZ) .

Fig 3: Special Tools (00 9 120) And (00 9 130)
G04751857Courtesy of BMW OF NORTH AMERICA, INC.
IMPORTANT: To avoid complaints of humming:

Before removing propeller shaft, mark cardan universal joint to drive flange of rear differential.

Reinstall joint in accordance with marking.

NOTE: Illustration similar
Fig 4: Mark On Universal Joint To Drive Flange
G04751858Courtesy of BMW OF NORTH AMERICA, INC.

Release screws.

Installation: 

Replace ZNS bolts.

NOTE: Illustration similar
Fig 5: Mounting Bolts
G04751859Courtesy of BMW OF NORTH AMERICA, INC.

Tighten down screws/bolts to specified torque.

Secure special tool angle of rotation 00 9 120 with magnet 00 9 130 to underbody and continue bolting according to angle of rotation.

For tightening torque refer to 26 11 4AZ in 26 11 PROPELLER SHAFT COMPLETE (4AZ-9AZ) .

Fig 6: Identifying Special Tool (00 9 120) And (00 9 130)
G04751860Courtesy of BMW OF NORTH AMERICA, INC.

Grip propeller shaft at center mount and release screws.

For tightening torque refer to 26 11 6AZ in 26 11 PROPELLER SHAFT COMPLETE (4AZ-9AZ) .

Detach propeller shaft from transmission output flange and remove towards bottom.

Fig 7: Propeller Shaft Bolts
G04751861Courtesy of BMW OF NORTH AMERICA, INC.

Installation: 

Check centering mount.

If necessary, replace damaged Centering Mount. 

Grease centering mount.