Overview - Timing Chain Cover
WARNING: This page is about a different car, the 2021 Volkswagen GTI, 2020 Volkswagen GTI, 2019 Volkswagen GTI, 2018 Volkswagen Golf, and 2018 Volkswagen GTI. However, it is still accessible from the selected car via links, so may be relevant.
- O-Ring
- Replace after removing.
- Lubricate with engine oil
- Oil Dipstick Tube
- Not Installed
- Not Installed
- Bolt
- Tightening Specifications and Sequence. Refer to Fig 2.
- Bolt
- Steel: 9 Nm
- Aluminum: 4 Nm + 45°
- Always replace aluminum bolts
- Camshaft Adjustment Valve 1 -N205-
- Removing and Installing. Refer to Camshaft Adjustment Valve 1 -N205- AND Exhaust Camshaft Adjustment Valve 1 -N318-, REMOVING AND INSTALLING .
- Bolt
- Steel: 9 Nm
- Aluminum: 4 Nm + 45°
- Always replace aluminum bolts
- Only for Engines: CHHB, CXDA, CXCA, CNTA, CXCB, DKFA and CXDB
- Exhaust Camshaft Adjustment Valve 1 -N318-
- Removing and Installing. Refer to Camshaft Adjustment Valve 1 -N205- AND Exhaust Camshaft Adjustment Valve 1 -N318-, REMOVING AND INSTALLING .
- Only for Engines: CHHB, CXDA, CXCA, CNTA, CXCB, DKFA and CXDB
- Seals
- Replace after removing.
- Installation position: smaller inner diameter outward
- Remove to replace the upper timing chain cover -item ) Upper Timing Chain Cover
- Lubricate with engine oil
- Seal
- Replace if damaged
- Cap
- Upper Timing Chain Cover
- Removing and Installing. Refer to UPPER TIMING CHAIN COVER, REMOVING AND INSTALLING .
- Seal
- Replace if damaged
- O-Rings
- Replace after removing.
- Coat with engine oil
- Alignment Pin
- For the lower timing chain cover
- Quantity: 2
- Bolt
- Lower Timing Chain Cover
- Replacing. Refer to LOWER TIMING CHAIN COVER, REMOVING AND INSTALLING .
- Seal
- For the vibration damper
- Replacing. Refer to VIBRATION DAMPER SEALING RING, REPLACING .
- Plugs
- Replace after removing.
Upper Timing Chain Cover - Tightening Sequence
-- Tighten the bolts -1 through 6- in the sequence shown:
| Step | Bolts | Tightening Specification/Additional Turn |
|---|---|---|
| 1. | -1 to 6- | Install all the way by hand |
| 2. | -1 to 6- | 9 Nm |
Lower Timing Chain Cover - Eight Bolt Tightening Sequence
-- Tighten the bolts -1 through 8- in three stages in the sequence shown:
| Step | Bolts | Steel Bolts | Aluminum Bolts |
|---|---|---|---|
| 1. | -1 through 8- | 8 Nm | 4 Nm |
| 2. | -2 to 3- and -5 to 8- | 45° additional turn | 45° additional turn |
| 3. | -1 and 4- | After installing the vibration damper tighten with an additional turn. | After installing the vibration damper tighten with an additional turn. |
Lower Timing Chain Cover - Tightening Sequence for 15 Bolts
-- Tighten the bolts -1 through 15- in three stages in the sequence shown:
| Step | Bolts | Steel Bolts | Aluminum Bolts |
|---|---|---|---|
| 1. | -1 through 15- | 8 Nm | 4 Nm |
| 2. | -1, 2, 4, 5- and -7 to 15- | 45° additional turn | 45° additional turn |
| 3. | -3 and 6- | After installing the vibration damper tighten with an additional turn. | After installing the vibration damper tighten with an additional turn. |