Engine And Transmission, Separating And Assembling
Special Tools And Workshop Equipment Required
- Shackle 10-222 A/12
- Shop Crane-Load Cap = 700-1200 KG VAS 6100
Conditions:
- The engine/transmission assembly is removed and is mounted on the engine Support T10359.
Separating
-- Remove the starter. Refer to Removal and Installation .
Vehicles with a Direct Shift Gearbox (DSG):
-- Remove the coolant hoses from the transmission oil cooler and seal off the openings.
Continuation for all Vehicles:
-- Disconnect all electrical connections from the transmission to the engine and free them up.
-- Install the Shackle 10-222 A/12 to the transmission and install the shop crane-load cap = 700-1200 KG VAS 6100 to the shackle, but do not lift yet.
-- Remove the upper engine/transmission bolts.
-- Before removing the last bolts, support the transmission with the shop crane.
-- Remove the lower engine/transmission bolts.
-- Separate the transmission from the engine; when doing this, guide the transmission.
Assembling
Assembly is performed in reverse order of removal; pay attention to the tightening specifications. Refer to the following:
- Refer to [For transmission(s) 02Q] Specifications .
- Refer to [For transmission(s) 02E] Specifications .