Evaporative Emission (EVAP) Canister Purge Regulator Valve N80 , checking
Special tools, testers and auxiliary items required
- Multimeter.
- Wiring diagram.
Test requirements
- The Evaporative Emission (EVAP) Canister Purge Regulator Valve N80 fuse OK.
- The ignition switched off.
- Voltage for the Evaporative Emission (EVAP) Canister Purge Regulator Valve N80 is supplied via the Fuse 43.
Test procedure
- Perform a preliminary check to verify the customers complaint. Refer to → Motronic Engine Control Module (ECM) J220 , replacing
Start diagnosis
- Remove the engine cover with air filter.
- Disconnect the Evaporative Emission (EVAP) Canister Purge Regulator Valve N80 electrical harness connector - arrow -.
Checking internal resistance
- Using a Multimeter , check the Evaporative Emission (EVAP) Canister Purge Regulator Valve N80 internal terminals 1 and 2 for resistance.
Specified value: 22.0 to 30.0 Ω.
If the specified value is not obtained:
- Replace the Evaporative Emission (EVAP) Canister Purge Regulator Valve N80.
If the specification is obtained:
Checking voltage supply
- Using a Multimeter , check the electrical harness connector terminal 1 to 2 for voltage.
- Operate the starter briefly.
Specified value: battery voltage.
If the specified value was not obtained:
- Using a Multimeter , check the electrical harness connector terminal 1 for voltage.
| Evaporative Emission (EVAP) Canister Purge Regulator Valve N80 electrical harness connector terminal | Measure to |
| 1 | Engine Ground (GND) |
- Operate the starter briefly.
Specified value: battery voltage.
If the specified value is not obtained:
- Check the wiring connection from the electrical harness connector terminal 1 to the Fuel Pump (FP) Relay J17 terminal 23/87 for an open circuit.
- Check the electrical harness connector for damage, corrosion, loose or broken terminals.
- If necessary, repair the wiring connection.
If the specified value was obtained:
Check Ground (GND) activation
- Using a Multimeter , check the electrical harness connector for voltage.
| Evaporative Emission (EVAP) Canister Purge Regulator Valve N80 electrical harness connector terminal | Measure to |
| 2 | Battery positive (+) |
- Operate the starter briefly.
Specified value: battery voltage.
- Switch the ignition off.
If the specified value was not obtained:
If the manufacturers test box is being used. Perform the following step.
- Install the Adapter F/VAG1598 (68 Pin) VAG1598/22. Refer to 24 MULTIPORT FUEL INJECTION (MFI) .
If the manufacturers test box is not being used. Perform the following step.
- Remove the Motronic Engine Control Module (ECM) J220. Refer to → Motronic Engine Control Module (ECM) J220 , replacing .
- Using a Multimeter , check the Evaporative Emission (EVAP) Canister Purge Regulator Valve N80 electrical connector terminal 2 to Motronic Engine Control Module (ECM) J220 electrical connector T80 terminal 15 for an open circuit.
| Evaporative Emission (EVAP) Canister Purge Regulator Valve N80 electrical harness connector terminal | Motronic Engine Control Module (ECM) J220 electrical harness connector T80 terminal test box socket |
| 2 | 15 |
Specified value: 1.5 Ω max.
If the specification is not obtained:
- Check the wiring for a short circuit to Battery positive (+) or an open circuit.
- Check the electrical harness connector for damage, corrosion, loose or broken terminals.
- If necessary, repair the wiring connection.
If the specification was obtained:
- Erase the DTC memory. Refer to → Diagnostic Mode 04: Reset/delete diagnostic data
- Perform a road test to verify repair.
If the DTC does not return:
Repair complete, Generate readiness code. Refer to → Readiness Code .
- End diagnosis.
If the DTC does return and no malfunction is detected in the wiring and the voltage supply was OK:
- Replace the Motronic Engine Control Module (ECM) J220. Refer to → Motronic Engine Control Module (ECM) J220 , replacing .
- Assembly is performed in the reverse of the removal.
- Install the engine cover with air filter.
Final procedures
After the repair work, the following work steps must be performed in the following sequence:
- Check the DTC memory. Refer to.
- If necessary, erase the DTC memory. Refer to.
- If the DTC memory was erased, generate readiness code. Refer to.
End of diagnosis