LEMON Manuals: Even more car manuals for everyone
Home >> Toyota >> 2021 >> Venza XLE >> Repair and Diagnosis >> Engine Mechanical >> Auxiliary Emission Control Systems >> Emission Control System - Service Information >> EGR Cooler >> Installation [10/2022 - ] >> Procedure

Installation [10/2022 - ]: Procedure

  1. INSTALL EGR COOLER ASSEMBLY 
    1. Using an 8 mm socket wrench, loosen the 4 bolts of the No. 1 EGR pipe sub-assembly.
      GTY1000348Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002

      HINT: 

      • As the bolts of the No. 1 EGR pipe sub-assembly are only to be loosened, it is not necessary to replace the EGR inlet gasket and EGR valve adapter gasket.
      • If the No. 1 EGR pipe sub-assembly is removed, it is necessary to replace the EGR inlet gasket and EGR valve adapter gasket with new ones.
    2. Using an 8 mm socket wrench, loosen the 2 bolts of the EGR valve assembly.
      GTY1001242Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
    3. Install a new EGR cooler gasket to the EGR cooler assembly.
      NOTE:

      Make sure that the claws of the EGR cooler gasket are toward the EGR cooler assembly side.

      GTY1105771Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
      *a Claw
    4. Install a new EGR valve gasket to the EGR cooler assembly.
      NOTE:

      Make sure that the claws of the EGR valve gasket are toward the EGR cooler assembly side.

    5. Type A:
      Fig 1: EGR Cooler Assembly Tightening Sequence
      GTY1105353Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
      *a Bolt or Nut
      1. Temporarily install the EGR cooler assembly to the cylinder head sub-assembly and EGR valve assembly with the 3 bolts and 2 nuts.
      2. Tighten the 3 bolts and 2 nuts in the order shown in the illustration.

        Torque: 24 N*m (245 kgf*cm, 18 ft.*lbf) 

    6. Type B:
      1. Temporarily install the EGR cooler assembly to the cylinder head sub-assembly and EGR valve assembly with the 2 bolts and 3 nuts.
      2. Tighten the 2 bolts and 3 nuts in the order shown in the illustration.

        Torque: 24 N*m (245 kgf*cm, 18 ft.*lbf) 

    7. Connect the No. 3 water by-pass hose and No. 4 water by-pass hose to the EGR cooler assembly and slide the 2 clips to secure them.
    8. Using an 8 mm socket wrench, tighten the 2 bolts of the EGR valve assembly.

      Torque: 10 N*m (102 kgf*cm, 7 ft.*lbf) 

    9. Using an 8 mm socket wrench, tighten the 4 bolts of the No. 1 EGR pipe sub-assembly.

      Torque: 10 N*m (102 kgf*cm, 7 ft.*lbf) 

  2. INSTALL INVERTER WITH CONVERTER ASSEMBLY 

    Refer to INSTALLATION [07/2020 - ]

  3. ADD ENGINE COOLANT (for Engine) 

    Refer to PROCEDURE - Step 2

  4. INSPECT FOR COOLANT LEAK (for Engine) 

    Refer to PROCEDURE - Step 1

  5. INSPECT FOR EXHAUST GAS LEAK 

    Refer to PROCEDURE - Step 5