Installation [08/2015 - 08/2017]: Procedure
- INSTALL COMBINATION METER ASSEMBLY
- Connect the connector and attach the wire harness clamp.
- Install the combination meter assembly with the 4 screws.
- INSTALL INSTRUMENT CLUSTER FINISH PANEL ASSEMBLY
Refer to PROCEDURE - Step 45
- INSTALL LOWER INSTRUMENT PANEL FINISH PANEL SUB-ASSEMBLY
Refer to PROCEDURE - Step 54
- INSTALL INSTRUMENT SIDE PANEL LH
Refer to PROCEDURE - Step 56
- INSTALL COWL SIDE TRIM BOARD LH
Refer to PROCEDURE - Step 46
- INSTALL FRONT DOOR SCUFF PLATE LH
Refer to PROCEDURE - Step 48
- CONNECT CABLE TO NEGATIVE BATTERY TERMINAL NOTE:
When disconnecting the cable some systems need to be initialized after the cable is reconnected (Refer to INITIALIZATION [08/2015 - 08/2017] ).
Torque: 5.4 N.m (55 kgf/cm, 48 in.lbf)
- CHECK SRS WARNING LIGHT
(Refer to DIAGNOSIS SYSTEM [08/2015 - 08/2017] )