Installation [04/2018 - 08/2020]: Procedure

  1. INSTALL COMBINATION METER ASSEMBLY 
    1. Connect the 2 connectors.
    2. Engage the clamp.
    3. Engage the 2 clips as shown in the illustration.
      GTY859830Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
      Install in this Direction
    4. Install the combination meter assembly with the 3 screws.
  2. INSTALL INSTRUMENT CLUSTER FINISH PANEL SUB-ASSEMBLY 

    Refer to PROCEDURE - Step 23

  3. INSTALL NO. 1 INSTRUMENT PANEL GARNISH SUB-ASSEMBLY 

    Refer to PROCEDURE - Step 24

  4. INSTALL LOWER INSTRUMENT PANEL FINISH PANEL ASSEMBLY 

    Refer to PROCEDURE - Step 25

  5. INSTALL INSTRUMENT CLUSTER FINISH PANEL GARNISH ASSEMBLY 

    Refer to PROCEDURE - Step 26

  6. INSTALL LOWER CENTER INSTRUMENT PANEL FINISH PANEL 

    Refer to PROCEDURE - Step 30

  7. INSTALL LOWER NO. 2 INSTRUMENT PANEL FINISH PANEL 

    Refer to PROCEDURE - Step 44

  8. INSTALL LOWER INSTRUMENT PANEL SUB-ASSEMBLY 

    Refer to PROCEDURE - Step 31

  9. INSTALL RADIO AND DISPLAY RECEIVER ASSEMBLY WITH BRACKET 

    Refer to PROCEDURE - Step 7

  10. INSTALL CENTER NO. 2 INSTRUMENT CLUSTER FINISH PANEL 

    Refer to PROCEDURE - Step 41

  11. INSTALL CENTER NO. 1 INSTRUMENT CLUSTER FINISH PANEL 

    Refer to PROCEDURE - Step 42

  12. INSTALL CONSOLE BOX BEZEL 

    Refer to PROCEDURE - Step 3

  13. INSTALL REAR UPPER CONSOLE PANEL SUB-ASSEMBLY 

    Refer to PROCEDURE - Step 5

  14. INSTALL SHIFT LEVER KNOB SUB-ASSEMBLY 

    Refer to PROCEDURE - Step 1

  15. INSTALL CENTER INSTRUMENT CLUSTER FINISH PANEL SUB-ASSEMBLY 

    Refer to PROCEDURE - Step 7

  16. INSTALL CONSOLE BOX POCKET SUB-ASSEMBLY 

    Refer to PROCEDURE - Step 8

  17. INSTALL FRONT CONSOLE UPPER PANEL GARNISH 

    Refer to PROCEDURE - Step 9

  18. INSTALL LOWER INSTRUMENT PANEL FINISH PANEL RH 

    Refer to PROCEDURE - Step 10

  19. INSTALL LOWER INSTRUMENT PANEL FINISH PANEL LH 

    Refer to PROCEDURE - Step 11

  20. INSTALL LOWER NO. 2 INSTRUMENT PANEL AIRBAG ASSEMBLY 

    Refer to INSTALLATION [04/2018 - 08/2020]

  21. CUSTOMIZE POWER TILT AND POWER TELESCOPIC STEERING COLUMN SYSTEM (for Power Tilt and Power Telescopic Steering Column) 

    Refer to PROCEDURE - Step 18