Installation [11/2018 - ]: Procedure
- INSTALL GENERATOR ASSEMBLY
- Install the generator assembly with the bolt and 2 nuts.
Torque: 25 N.m (255 kgf/cm, 18 ft.lbf)
- Install the wire harness clamp bracket to the generator assembly with the bolt.
Torque: 10 N.m (102 kgf/cm, 7 ft.lbf)
- Connect the wire harness to terminal B with the nut.
Torque: 9.8 N.m (100 kgf/cm, 87 in.lbf)
- Close the terminal cap.
- Connect the generator assembly connector.
- Install the generator assembly with the bolt and 2 nuts.
- INSTALL V-RIBBED BELT
Refer to INSTALLATION [11/2018 - ]
- INSTALL INLET AIR CLEANER ASSEMBLY
Refer to PROCEDURE - Step 3 [11/2018 - 08/2020] , or refer to PROCEDURE - Step 3 [08/2020 - ]
- CONNECT CABLE TO NEGATIVE BATTERY TERMINAL NOTE:
When disconnecting the cable, some systems need to be initialized after the cable is reconnected.
Refer to INITIALIZATION [11/2018 - 02/2019] , or refer to INITIALIZATION [02/2019 - 10/2019] , or refer to INITIALIZATION [10/2019 - 06/2020] , or refer to INITIALIZATION [06/2020 - 08/2020] , or refer to INITIALIZATION [08/2020 - 12/2021] , or refer to INITIALIZATION [12/2021 - 10/2022] , or refer to INITIALIZATION [10/2022 - 10/2023] , or refer to INITIALIZATION [10/2023 - ]