Installation [09/2016 - ]: Procedure
- INSTALL EV CHARGER LID INDICATOR ASSEMBLY
- Install the EV charger lid indicator assembly to the battery charger connector opening lid sub-assembly with the 2 bolts.
Torque: 2.0 N*m (20 kgf*cm, 18 in.*lbf)
- Install the EV charger lid indicator assembly to the battery charger connector opening lid sub-assembly with the 2 bolts.
- INSTALL FUEL FILLER OPENING LID LOCK BRACKET
Refer to INSTALLATION [09/2016 - 05/2019] , or refer to INSTALLATION [05/2019 - 07/2020] , or refer to INSTALLATION [07/2020 - ]