Installation [11/2015 -]: Procedure
- INSTALL SHIFT LOCK CONTROL UNIT ASSEMBLY
- Connect the shift lock control unit assembly connector.
- Install the shift lock control unit assembly to the No. 1 instrument panel brace sub-assembly and No. 2 instrument panel brace sub-assembly with the 3 nuts.
Torque: 12 N.m (122 kgf.cm, 9 ft./lbf)
- Engage the clamp.
- INSTALL NO. 2 LOWER INSTRUMENT PANEL FINISH PANEL
Refer to PROCEDURE - Step 6 [11/2015 - 11/2017] , or refer to PROCEDURE - Step 6 [11/2017 - 08/2019] , or refer to PROCEDURE - Step 6 [08/2019 -]
- INSTALL SHIFT LEVER HOLE COVER
Refer to PROCEDURE - Step 7 [11/2015 - 11/2017] , or refer to PROCEDURE - Step 7 [11/2017 - 08/2019] , or refer to PROCEDURE - Step 7 [08/2019 -]
- INSTALL LOWER CENTER INSTRUMENT CLUSTER FINISH PANEL SUB-ASSEMBLY
Refer to PROCEDURE - Step 8 [11/2015 - 11/2017] , or refer to PROCEDURE - Step 8 [11/2017 - 08/2019] , or refer to PROCEDURE - Step 8 [08/2019 -]
- INSTALL LOWER NO. 1 INSTRUMENT PANEL AIRBAG ASSEMBLY
Refer to PROCEDURE - Step 1
- INSTALL LOWER INSTRUMENT PANEL FINISH PANEL ASSEMBLY
Refer to PROCEDURE - Step 20 [11/2015 - 11/2017] , or refer to PROCEDURE - Step 22 [11/2017 - 08/2019] , or refer to PROCEDURE - Step 21 [08/2019 -]
- CONNECT HOOD LOCK CONTROL LEVER SUB-ASSEMBLY
Refer to PROCEDURE - Step 21 [11/2015 - 11/2017] , or refer to PROCEDURE - Step 23 [11/2017 - 08/2019] , or refer to PROCEDURE - Step 22 [08/2019 -]
- INSTALL NO. 1 INSTRUMENT PANEL UNDER COVER SUB-ASSEMBLY
Refer to PROCEDURE - Step 22 [11/2015 - 11/2017] , or refer to PROCEDURE - Step 24 [11/2017 - 08/2019] , or refer to PROCEDURE - Step 23 [08/2019 -]
- INSTALL COWL SIDE TRIM BOARD LH
Refer to PROCEDURE - Step 50 [11/2015 - 12/2018] , or refer to PROCEDURE - Step 46 [12/2018 - 07/2020] , or refer to PROCEDURE - Step 46 [07/2020 -]
- INSTALL FRONT DOOR SCUFF PLATE LH
Refer to PROCEDURE - Step 51 [11/2015 - 12/2018] , or refer to PROCEDURE - Step 47 [12/2018 - 07/2020] , or refer to PROCEDURE - Step 47 [07/2020 -]
- INSTALL INSTRUMENT CLUSTER FINISH PANEL GARNISH ASSEMBLY
Refer to PROCEDURE - Step 25 [11/2015 - 11/2017] , or refer to PROCEDURE - Step 27 [11/2017 - 08/2019] , or refer to PROCEDURE - Step 26 [08/2019 -]
- INSTALL INSTRUMENT PANEL FINISH PANEL END LH
Refer to PROCEDURE - Step 26 [11/2015 - 11/2017] , or refer to PROCEDURE - Step 28 [11/2017 - 08/2019] , or refer to PROCEDURE - Step 27 [08/2019 -]
- INSTALL REAR CONSOLE BOX ASSEMBLY
Refer to INSTALLATION [11/2015 - 12/2018] , or refer to INSTALLATION [12/2018 -]
- CONNECT CABLE TO NEGATIVE AUXILIARY BATTERY TERMINAL NOTE:
When disconnecting the cable, some systems need to be initialized after the cable is reconnected.
Refer to INITIALIZATION [11/2015 - 11/2017] , or refer to INITIALIZATION [11/2017 - 12/2018] , or refer to INITIALIZATION [12/2018 - 08/2019] , or refer to INITIALIZATION [08/2019 - 07/2020] , or refer to INITIALIZATION [07/2020 -]
- INSPECT SHIFT LEVER
- Turn the power switch on (READY).
- Check that all shift positions can be selected by moving the shift lever.
HINT:
After the shift lock control unit assembly is replaced with a new one, perform the above operation. If this operation is not performed, moving the shift lever may not initially select shift positions.