Installation [11/2016 - ]: Procedure
- INSTALL STEERING GEAR HEAT INSULATOR (for 2GR-FKS)
- Install the steering gear heat insulator to the steering link assembly with the bolt.
Torque: 6.0 N*m (61 kgf*cm, 53 in.*lbf)
- Install the steering gear heat insulator to the steering link assembly with the bolt.
- INSTALL TIE ROD ASSEMBLY LH
- INSTALL TIE ROD ASSEMBLY RH
HINT:
Perform the same procedure as for the LH side.
- INSTALL STEERING LINK ASSEMBLY
- Install the steering link assembly to the front frame assembly with the 2 bolts and 2 nuts.
Torque: 70 N*m (714 kgf*cm, 52 ft.*lbf)
NOTE:- Make sure to tighten the bolts starting from the steering link assembly pinion shaft side.
- Keep the nut from rotating while turning the bolt because the nut has its own stopper.
- Install the steering link assembly to the front frame assembly with the 2 bolts and 2 nuts.
- INSTALL FRONT NO. 2 STABILIZER BRACKET LH
Refer to PROCEDURE - Step 5
- INSTALL FRONT NO. 2 STABILIZER BRACKET RH
HINT:
Perform the same procedure as for the LH side.
- INSTALL FRONT STABILIZER BAR
- Install the front stabilizer bar with 2 front No. 2 stabilizer brackets and 2 front No. 1 stabilizer bar bushings to the front frame assembly.
- INSTALL FRONT NO. 1 STABILIZER BRACKET LH
Refer to PROCEDURE - Step 8
- INSTALL FRONT NO. 1 STABILIZER BRACKET RH
HINT:
Perform the same procedure as for the LH side.
- INSTALL FRONT STABILIZER LINK ASSEMBLY LH
- Install the front stabilizer link assembly LH to the front stabilizer bar with the nut.
Torque: 74 N*m (755 kgf*cm, 55 ft.*lbf)
HINT:
If the ball joint turns together with the nut, use a 6 mm hexagon wrench to hold the stud bolt.
- Install the front stabilizer link assembly LH to the front stabilizer bar with the nut.
- INSTALL FRONT STABILIZER LINK ASSEMBLY RH
HINT:
Perform the same procedure as for the LH side.
- CONNECT TIE ROD ASSEMBLY LH
- CONNECT TIE ROD ASSEMBLY RH
HINT:
Perform the same procedure as for the LH side.
- CONNECT STEERING INTERMEDIATE SHAFT ASSEMBLY
- INSTALL NO. 2 ENGINE UNDER COVER
for 1AR-FE: Refer to PROCEDURE - Step 80
for 2GR-FKS: Refer to PROCEDURE - Step 102
- INSTALL FRONT WHEELS
Torque: 103 N*m (1050 kgf*cm, 76 ft.*lbf)
- INSPECT AND ADJUST FRONT WHEEL ALIGNMENT
Refer to ADJUSTMENT [11/2016 - ]
- INSPECT STEERING WHEEL CENTER POINT