Power Switch Illumination Circuit [10/2014 - 10/2015]: Procedure
- PERFORM ACTIVE TEST USING TECHSTREAM
- Connect the Techstream to the DLC3.
- Turn the power switch on (IG).
- Turn the Techstream on.
- Enter the following menus: Body Electrical / Smart Key / Active Test.
- Perform the Active Test according to the display on the Techstream.SMART KEY
Tester Display Test Part Control Range Diagnostic Note Power/Engine SW Light Power switch illumination OFF/ON When performing this Active Test, make sure the following condition is met:
The power switch illumination is off (15 seconds or more have elapsed since it turned from on to off) and the power switch is on (ACC) or on (IG), or the engine is running.OK
Power switch illumination comes on.
Result:
OK
PROCEED TO NEXT SUSPECTED AREA SHOWN IN PROBLEM SYMPTOMS TABLE
(Refer to PROBLEM SYMPTOMS TABLE [10/2014 - 10/2015] )
Result:
NG
See step 2
- INSPECT POWER SWITCH
- Remove the power switch (Refer to REMOVAL [10/2014 - ] ).
- Inspect the power switch (Refer to INSPECTION [10/2014 - ]
).
OK
Power switch illumination is normal.
Result:
NG
REPLACE POWER SWITCH
(Refer to REMOVAL [10/2014 - ] )
Result:
OK
See step 3
- CHECK HARNESS AND CONNECTOR (POWER SWITCH - CERTIFICATION ECU (SMART KEY ECU ASSEMBLY))
- Disconnect the D109 and D110 certification ECU (smart key ECU assembly) connectors.
- Disconnect the D46 power switch connector.
- Measure the resistance according to the value(s) in the table below.
Standard Resistance
Tester Connection Condition Specified Condition D46-9 (SWIL) - D110-16 (SWIL) Always Below 1 Ω D46-6 (AGND) - D109-6 (AGND) Always Below 1 Ω D46-9 (SWIL) - Body ground Always 10 kΩ or higher D46-6 (AGND) - Body ground Always 10 kΩ or higher
Result:
OK
REPLACE CERTIFICATION ECU (SMART KEY ECU ASSEMBLY)
(Refer to REMOVAL [10/2014 - ] )
Result:
NG
REPAIR OR REPLACE HARNESS OR CONNECTOR