LEMON Manuals: Even more car manuals for everyone
Home >> Toyota >> 2009 >> Corolla S, 1.8 L, Standard >> Repair and Diagnosis >> External Pages >> Different variant/trim >> Section 10 (Automatic Transmission - U341E) >> Valve Body Assembly >> Inspection

Valve Body Assembly: Inspection

WARNING: This page is about a different variant/trim than selected.
  1. INSPECT SHIFT SOLENOID VALVE S1 
    1. Measure the resistance according to the value(s) in the table below.

      Standard Resistance 

      TESTER CONNECTION SPECIFIED CONDITION CHART

      Tester Connection Condition Specified Condition
      Solenoid Connector (S1) - Solenoid Body (S1) 15 to 25°C (59 to 77°F) 11 to 15 Ω

      If the value is not as specified, replace the shift solenoid valve S1.

      Fig 1: Inspecting Shift Solenoid Valve S1
      G05400378Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
    2. Connect a positive (+) battery lead to the terminal of the solenoid connector, and a negative (-) battery lead to the solenoid body, and check the operation of the valve.
    NOTE: When using battery voltage during this inspection, do not bring the positive and negative tester probes too close to each other as a short circuit may occur.

    OK: 

    The solenoid makes an operating sound. 

    If the operation cannot be done as specified, replace the shift solenoid valve S1.

  2. INSPECT SHIFT SOLENOID VALVE S2 
    1. Measure the resistance according to the value(s) in the table below.

      Standard Resistance 

      TESTER CONNECTION SPECIFIED CONDITION CHART

      Tester Connection Condition Specified Condition
      Solenoid Connector (S2) - Solenoid Body (S2) 15 to 25°C (59 to 77°F) 11 to 15 Ω

      If the value is not as specified, replace the shift solenoid valve S2.

    2. Connect a positive (+) battery lead to the terminal of the solenoid connector, and a negative (-) battery lead to the solenoid body, and check the operation of the valve.
    NOTE: When using battery voltage during this inspection, do not bring the positive and negative tester probes too close to each other as a short circuit may occur.

    OK: 

    The solenoid makes an operating sound. 

    Fig 2: Inspecting Shift Solenoid Valve S2
    G05400379Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002

    If the operation cannot be done as specified, replace the shift solenoid valve S2.

  3. INSPECT SHIFT SOLENOID VALVE ST 
    1. Measure the resistance according to the value(s) in the table below.

      Standard Resistance 

      TESTER CONNECTION SPECIFIED CONDITION CHART

      Tester Connection Condition Specified Condition
      Solenoid Connector (ST) - Solenoid Body (ST) 15 to 25°C (59 to 77°F) 11 to 15 Ω

      If the value is not as specified, replace the shift solenoid valve ST.

      Fig 3: Inspecting Shift Solenoid Valve ST
      G05400380Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
    2. Connect a positive (+) battery lead to the terminal of the solenoid connector, and a negative (-) battery lead to the solenoid body, and check the operation of the valve.
    NOTE: When using battery voltage during this inspection, do not bring the positive and negative tester probes too close to each other as a short circuit may occur.

    OK: 

    The solenoid makes an operating sound. 

    If the operation cannot be done as specified, replace the shift solenoid valve ST.

  4. INSPECT SHIFT SOLENOID VALVE SLT 
    1. Measure the resistance according to the value(s) in the table below.

      Standard Resistance 

      TESTER CONNECTION SPECIFIED CONDITION CHART

      Tester Connection Condition Specified Condition
      1-2 20°C (68°F) 5.0 to 5.6 Ω

      If the value is not as specified, replace the shift solenoid valve SLT.

    2. Connect a positive (+) battery lead with a 21 W bulb to terminal 2 and a negative (-) battery lead to terminal 1 of the solenoid valve connector, and check the operation of the valve.
    NOTE: When using battery voltage during this inspection, do not bring the positive and negative tester probes too close to each other as a short circuit may occur.

    OK: 

    The solenoid makes an operating sound. 

    If the operation cannot be done as specified, replace the shift solenoid valve SLT.

    Fig 4: Inspecting Shift Solenoid Valve SLT
    G05400381Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
  5. INSPECT SHIFT SOLENOID VALVE SLU 
    1. Measure the resistance according to the value(s) in the table below.

      Standard Resistance 

      TESTER CONNECTION SPECIFIED CONDITION CHART

      Tester Connection Condition Specified Condition
      1 - 2 20°C (68°F) 5.0 to 5.6 Ω

      If the value is not as specified, replace the shift solenoid valve SLU.

    2. Connect a positive (+) battery lead with a 21 W bulb to terminal 2 and a negative (-) battery lead to terminal 1 of the solenoid valve connector, and check the operation of the valve.
    NOTE: While using battery voltage during this inspection, do not bring the positive and negative tester probes too close to each other as a short circuit may occur.

    OK: 

    The solenoid makes an operating sound. 

    If the operation cannot be done as specified, replace the shift solenoid valve SLU.

    Fig 5: Inspecting Shift Solenoid Valve SLU
    G06012100Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002