Emission Control System: Canister: Inspection
- INSPECT CANISTER
- Visually check the canister for cracks or damage. If cracks or damage are found, replace the canister.
- Check the canister operation.
- With the purge port closed, blow 2 kPa (20 gf/cm2
, 0.3 psi) of air into the vent port, and check that air flows from the air inlet port.
If the result is not as specified, replace the canister.
- With the vent port closed, blow 1 kPa (10 gf/cm2
, 0.2 psi) of air inlet port, and check that air flows from the purge port.
If the result is not as specified, replace the canister.
- With the purge port closed, blow 2 kPa (20 gf/cm2
, 0.3 psi) of air into the vent port, and check that air flows from the air inlet port.
- Check for air leaks.
- Remove the air hose between ports A and B.
- Connect a pressure gauge to the vent port of the canister.
- With port B, the purge port and air inlet port closed and port A open, apply 20 kPa (0.2 kgf/cm2
, 2.9 psi) of pressurized air into the vent port, then confirm that pressure is retained for 1 minute.