Inspection Procedure
WARNING: This page is about a different variant/trim than selected.
- Check transmission wire.
PREPARATION:
Disconnect the transmission wire connector.
CHECK:
Measure resistance between S2 of transmission wire connector and body ground.
OK:
- Resistance: 11 to 15 Ω at 20°C (68°F)
- NG: Go to 3
- OK: Go to next step
- Measure resistance between terminal S2 of ECM connector and body ground.
PREPARATION:
- Connect the transmission wire connector.
- Disconnect the ECM connector.
CHECK:
Measure resistance between terminals S2 of ECM connector and body ground.
OK:
- Resistance: 11 to 15 Ω at 20°C (68°F)
- NG: Repair or replace the harness or connector ( HOW TO USE THE DIAGNOSTIC CHART AND INSPECTION PROCEDURE ).
- OK: Replace the ECM.
- Check shift solenoid valve S2 (No. 2) operation.
Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
PREPARATION:
- Jack up the vehicle.
- Remove the oil pan.
- Remove the shift solenoid valve S2 (No. 2).
CHECK:
Measure the resistance between the solenoid connector terminal and the body ground.
OK:
- Resistance: 11 to 15 Ω at 20°C (68 °F)
CHECK:
Connect the battery positive lead to the solenoid connector terminal and the battery negative lead to the solenoid body ground.
OK:
- Solenoid sounds operation noise.
Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
- NG: Replace the shift solenoid valve S2 (No. 2).
- OK: Repair or replace the transmission wire ( ATF TEMPERATURE SENSOR ).