Inspection Procedure
WARNING: This page is about a different variant/trim than selected.
- INSPECT TRANSMISSION WIRE (SL1)
- Disconnect the transmission wire connector from the transaxle.
- Measure the resistance according to the value (s) in the table below.
Standard:
SPECIFIED CONDITIONTester Connection Specified Condition 20 "C (68°F) 5 (SL1+)- 10 (SL1-) 5.0 to 5.6Ω - Measure the resistance according to the value (s) in the table below.
Standard (Check for short):
- NG: Go to step 3
- OK: GO TO NEXT STEP.
- CHECK HARNESS AND CONNECTOR TRANSMISSION WIRE - ECM)
- Connect the transmission connector to the transaxle.
- Disconnect the connector from the ECM.
- Measure the resistance according to the value (s) in the table below.
Standard:
SPECIFIED CONDITIONTester Connection Specified Condition 20°C (68°F) E8 - 19 (SL1+) - E8 - 18 (SL1-) 5.0 to 5.6Ω - Measure the resistance according to the value (s) in the J table below.
Standard (Check for short):
- NG: REPAIR OR REPLACE HARNESS OR CONNECTOR (See ELECTRONIC CIRCUIT INSPECTION PROCEDURE )
- OK: REPLACE ECM (See REPLACEMENT )
- INSPECT SHIFT SOLENOID VALVE (SLI)
- Remove the shift solenoid valve SL1.
- Measure the resistance according to the value (s) in the table below.
Standard:
SPECIFIED CONDITIONTester Connection Specified Condition 20°C (68°F) 1 - 2 5.0 to 5.6Ω - Connect the positive (+) lead with a 21 W bulb to terminal 2 and the negative (-) lead to terminal 1 of the solenoid valve connector, then check the movement of the valve.
OK: The solenoid makes an operating noise.
- NG: REPLACE SHIFT SOLENOID VALVE (SLI)
- OK: REPAIR OR REPLACE TRANSMISSION WIRE (See REPLACEMENT )