Intake Duct No. 1
WARNING: This page is about a different variant/trim than selected.
• Except for Canada
Install the vacuum hose, blow-by diagnosis connector harness and wastegate control solenoid valve to the intake duct No. 1.
NOTE:
- Use new O-rings.
- Check that the wastegate control solenoid valve is securely seated.
Tightening torque:
2.8 N.m (0.3 kgf-m, 2.1 ft-lb)
• For Canada
- Set the connector bracket, and using new set bolts, tighten the bolt until the bolt head is broken (bolt head wrenched off).NOTE: This operation is required only when replacing the intake duct No. 1.
- Install the wastegate control solenoid valve and air by-pass pipe to the intake duct No. 1.NOTE:
- Use new O-rings.
- Check that the wastegate control solenoid valve is securely seated.
Tightening torque:
T1: 2.5 N.m (0.3 kgf-m, 1.8 ft-lb)
T2: 6.4 N.m (0.7 kgf-m, 4.7 ft-lb)
- Install the vacuum hose and blow-by diagnosis connector harness to the intake duct No. 1.