Pour in coolant and bleed cooling system - AR20.00-P-1142-04A
ENGINE 133, 152, 155, 156, 157, 159, 177, 178, 270, 271, 272, 273, 274, 275, 276, 277, 278, 279
ENGINE 157, 176, 642
ENGINE 607, 628, 629, 642, 651
Engine 133, 157, 274, 276.8, 278
Engine 157, 176
Engine 177, 178
Engine 642, 651
Also repeat the ventilation process for the low-temperature circuit.
Only ventilate the engine cooling system for a cold engine.
The drainage container for NTKL adaptation (13) should be emptied after beginning work.
Shown on engine cooling system main circuit in model 171
- Bring coolant reservoir (4a) of the
vacuum-type cooling system filler to the same height as the coolant expansion reservoir (1).
Unscrew cooling system closure cap (10) and screw on tester cap (2) at coolant expansion reservoir (1).
- Attach the control unit (3) to the
tester cap (2).
- Attach Venturi nozzle (9) to control unit (3).
- Close drain valve (8) and feed valve (7).
- Place feed hose (4) of the coolant on the coolant reservoir (4).
In order to avoid suctioning up of air in coolant reservoir (4a) and for completeness of the filling capacity of the engine cooling system in the vehicle, always completely fill up the coolant reservoir (4a).
- Guide waste air hose (5) into an empty container (5a).
- Connect compressed air hose (6) to the Venturi nozzle (9) and apply pressure.
The overpressure in the compressed air supply must be at least about 8 bar so that sufficient vacuum can be generated through the Venturi nozzle (9).
- Open the drain valve (8).
A vacuum is created in the engine cooling system.
- Open feed valve (7) until feed hose (4) has filled with coolant and subsequently close feed valve (7) again.
- Close drain valve (8) if display of the control unit (3) is in the green area.
- Remove compressed air hose (6) from the Venturi nozzle (9) and monitor if the vacuum remains stable for 30 seconds.
If this is not the case
Check hoses and connections for damage, repair if necessary and again create a vacuum
- Close feed valve (7) and drain valve (8).
- Bring switch (11) of the
electrical vacuum pump (18) in position 0.
- Connect the positive and negative terminal of the electrical vacuum pump (18) using a suitable 12 V voltage source.
Observe polarity of the positive and negative terminal of the
electrical vacuum pump (18).
- Hook bracket (12) into the
NTKL adaptation (13).
- Connect hose (14) to the
NTKL adaptation (13).
- Close off shutoff valves (15, 16, 17).
- Attach hose (20) to the
NTKL adaptation (13).
- Decouple venturi nozzle (9) and replace by a hose (20).
Switch in electrical vacuum pump (18) and open stopcock (15).
The vacuum indicator (19) must indicate at least -0.9 bar.
- Open the drain valve (8).
The feed valve (7) must remain closed.
Evacuate the whole engine cooling system for 5 minutes. The indicator for the vacuum indicator (19) must be above the -0.9 bar marking.
- Close drain valve (8).
Switch off electrical vacuum pump (18).
Bring switch (11) of the
electrical vacuum pump (18) in position 0.
- Remove hose (14) and display vacuum in
NTKL adaptation (13) until the display (19) displays 0.0 bar.
- Check the whole engine cooling system by means of a visual inspection for 30 s for leaktightness.
Shown on engine cooling system main circuit in model 231
- Open feed valve (7).
The engine cooling system is filled.
Filling is complete when the control unit (3) shows 0.0 bar.
- Open drain valve (8) if coolant is no longer suctioned.
- Remove control unit (3) along with all connections and
tester cap (2).
- Screw cooling system cap (10) onto coolant expansion reservoir (1).
- Correct coolant level in coolant expansion reservoir (1).