Installing Compressor
Information
Check the following before installing the air line:
- Check that the cutting ring -1- and Voss threaded joint -2- are on the air line -3- (not relevant if the component was replaced and the Voss threaded joint that is pre-fitted on the component is used).
- Check that the air line is fitted correctly.
Check: Air line connection
Only one marking -1- on the air line should be visible.
Pull the air line briefly against the insertion direction. If it cannot be pulled out, the air line is fitted correctly.
Check: Air line fitted correctly
- Installation is performed in reverse order. Pay particular attention to the following:
- 1.1 Tighten screws -1-
.
> Tightening - torque 20 Nm (15 ftlb.)
Mounting for compressor holder and valve unit
- 1.2 Tighten union nut -2-
.
> Tightening - torque 3.5 Nm (2.5 ftlb.)
Lines on compressor
- 1.3 Tighten union nuts -1-
.
> Tightening - torque 3.5 Nm (2.5 ftlb.)
Pressure lines to valve block
- 1.1 Tighten screws -1-
.