Home >> Porsche >> 2021 >> Taycan Base >> Repair and Diagnosis >> Hybrid/Electric Powertrain >> Electric Converters and Controllers >> 27 Starter, Power Supply, Cruise Control 2.0L (2 Of 2) -- Y1A - TAYCAN (Y1A) >> WM, 279219 Removing And Installing Elect. Machine (Rotor Position Sensor) >> Subsequent Work

Subsequent Work

WARNING: Incorrect handling of high-voltage components 
  • Electric shock 
  • Short circuit 
  • Fire 
  • Explosion 

    → Only appropriately trained and authorised persons are permitted to work on high-voltage vehicles and components.

    → Required qualification: High voltage technician or high voltage expert.

    → Observe national requirements and legislation for this work.

    → Always use insulated tools, e.g. > VAS 6883 - Insulated Tool Set  when working on these components. Observe general warning notes for working on the high-voltage system.

    > 2X00IN GENERAL WARNING NOTES FOR WORKING ON THE HIGH-VOLTAGE SYSTEM

  1. Install power electronics.

    > 279119 REMOVING AND INSTALLING REAR POWER ELECTRONICS 

  2. Fasten electric motor with automatic transmission on the assembly support.

    > 279213 FASTENING ELECTRIC MOTOR WITH AUTOMATIC TRANSMISSION ON THE ASSEMBLY SUPPORT 

  3. Install automatic transmission (with electric motor).

    > 373519 REMOVING AND INSTALLING AUTOMATIC TRANSMISSION (WITH ELECTRIC MOTOR)

  4. Observe general warning notes for working on the high-voltage system.

    > 2X00IN GENERAL WARNING NOTES FOR WORKING ON THE HIGH-VOLTAGE SYSTEM

  5. Installing rear axle

    > 420119 REMOVING AND INSTALLING REAR AXLE

  6. Secure ground strap for battery.

    > 978519 REMOVING AND INSTALLING GROUND STRAP FOR BATTERY

  7. Perform potential equalization measurement.

    > 2X00IN PERFORMING POTENTIAL EQUALIZATION MEASUREMENT (FOUR-WIRE MEASUREMENT)

  8. Refill coolant.

    > 193817 DRAINING AND FILLING COOLANT

  9. Start the high-voltage system.

    > 2X00IN ACTIVATION/COMMISSIONING HIGH-VOLTAGE SYSTEM

  10. Complete the required documentation for starting the high-voltage system.

    > 2X00IN TEST LOG: STARTING THE HIGH-VOLTAGE SYSTEM