15 Engine - Cylinder Head, Valve Drive 4.0L Turbo Gas -- 971 - PANAMERA (971)
>>
WM, 154719 Removing And Installing Guide And TENSIONING Rails (V8 BITURBO)
>>
Installing Guide And TENSIONING Rails
>>
Installing Guide And Tensioning Rails For Cylinder Bank 1
Installing Guide And Tensioning Rails For Cylinder Bank 1
Information
Check length of timing chains:
The timing chains have different lengths.
Bank 1: 122 links
Bank 2: 124 links
Installation is performed in reverse order. Pay particular attention to the following:
1.1 Fit short timing chain.
Courtesy of PORSCHE CARS NORTH AMERICA, INC.
Guide and tensioning rails for cylinders 1 to 4