Home >> Porsche >> 2019 >> Cayenne Base >> Repair and Diagnosis >> External Pages >> Different car >> Section 16 (6X Body-Equipment Outside-General (Coupe) -- 9YB - Cayenne (9YB)) >> WM, 6X00IN22 Using PORSCHE 2-Component Window Adhesive >> Working With PORSCHE 2-Component Window Adhesive >> Preparing Vehicle Flange - Vehicle Flange With Repair Paint Finish Without Adhesive Bead

Preparing Vehicle Flange - Vehicle Flange With Repair Paint Finish Without Adhesive Bead

WARNING: This page is about a different car, the 2023 Porsche Cayenne, 2022 Porsche Cayenne, 2021 Porsche Cayenne, and 2020 Porsche Cayenne. However, it is still accessible from the selected car via links, so may be relevant.
  1. Create repair paint finish in the vehicle flange area.
    1. 1.1  Apply 2-component primer to the bare panel in the vehicle flange area.
    2. 1.2  Allow primer to dry.
    3. 1.3  Mask the bonding area around the vehicle flange with adhesive tape. Do not apply colored paint to the bonding area.
    4. 1.4  Paint the vehicle flange and the remaining affected components with a standard repair paint finish and allow to dry.
    5. 1.5  Finally, remove adhesive tape used to mask the area.
  2. Clean the bonding area on the vehicle flange using a cleaning cloth from the adhesive set.
    G15239197Courtesy of PORSCHE CARS NORTH AMERICA, INC.

    Cleaning cloth

  3. Let cleaning agent air dry for 10 minutes.
    G15239198Courtesy of PORSCHE CARS NORTH AMERICA, INC.

    Cleaning agent drying time

  4. Shake primer for 2 minutes. The steel ball must be clearly heard and felt moving inside the primer cartridge.
    G15239199Courtesy of PORSCHE CARS NORTH AMERICA, INC.

    Primer

  5. Apply a single coat of primer from the adhesive set in the bonding area on the vehicle flange in one movement using the applicator brush.
    G15239200Courtesy of PORSCHE CARS NORTH AMERICA, INC.

    Primer on vehicle flange

  6. Let air dry for 15 minutes.
    G15239201Courtesy of PORSCHE CARS NORTH AMERICA, INC.

    Primer drying time

  7. If a drying time of 8 hours is exceeded:  Primer may be applied only once and within 96 hours  of applying the first coat of primer. Primed bonding surfaces must be protected from external influences and dirt during this period. Let primer air dry for 15 minutes again.