WARNING: This page is about a different variant/trim than selected.
  1. Secure charge-air cooler - -.
    1. 1.1 Fit fastening screws - - and tighten to > Tightening torque 10 Nm  .
    2. 1.2 Connect vacuum lines - - to the charge-air cooler - -.
    G14945821Courtesy of PORSCHE CARS NORTH AMERICA, INC.
  2. Install engine compartment lid.

    > WM, 557819 REMOVING AND INSTALLING ENGINE COMPARTMENT LID

  3. Remove protective covers from the vehicle.