Home >> Porsche >> 2017 >> Panamera Base >> Repair and Diagnosis >> External Pages >> Different variant/trim >> Section 61 (15 Engine - Cylinder Head, Valve Drive 4.0L Turbo Gas -- 971 - PANAMERA (971)) >> WM, 154719 Removing And Installing Guide And TENSIONING Rails (V8 BITURBO) >> Installing Guide And TENSIONING Rails >> Installing Guide And Tensioning Rails For Cylinder Bank 1

Installing Guide And Tensioning Rails For Cylinder Bank 1

WARNING: This page is about a different variant/trim than selected.

Information 

Check length of timing chains:

  1. Installation is performed in reverse order. Pay particular attention to the following:
    1. 1.1 Fit short timing chain.
      G15824546Courtesy of PORSCHE CARS NORTH AMERICA, INC.

      Guide and tensioning rails for cylinders 1 to 4