Subsequent Work
WARNING: This page is about a different variant/trim than selected.
- Install pressure pipe.
> WM, 214119 REMOVING AND INSTALLING PRESSURE PIPE (V8 BITURBO) "INSTALLING "
- Install intake manifold.
> WM, 212419 REMOVING AND INSTALLING INTAKE PIPE (V8 BITURBO) "INSTALLING "
- Install oxygen sensor on the turbocharger.
> 246919 REMOVING AND INSTALLING OXYGEN SENSOR UPSTREAM OF CATALYTIC CONVERTER (V8 BITURBO)
- Install primary catalytic converter at the right.
> 267619 REMOVING AND INSTALLING PRIMARY CATALYTIC CONVERTER (V8 BITURBO) - SECTION ON "INSTALLING"
- If the turbocharger on bank 5-8 was removed, position and tighten the connecting clamp for the primary catalytic converter at the left (bank 5-8).
> Tightening torque 7 Nm (5 ftlb.) +/- 1 Nm (0.5 ftlb.)
- 5.1 Then install the turbocharger on bank 1-4.
- Checking engine-oil level.
- Check engine coolant level.