Subsequent Work For Removing And Installing Engine
WARNING: This page is about a different car, the 2014 Porsche Cayenne, 2013 Porsche Cayenne, 2012 Porsche Cayenne, and 2011 Porsche Cayenne. However, it is still accessible from the selected car via links, so may be relevant.
- On vehicles with 19-inch brake system: Fit the air guide at the anti-roll bar.
> 407719 Removing and installing anti-roll bar - "INSTALLING "
- Fit front wheel housing liners.
> WM 505619 REMOVING AND INSTALLING FRONT WHEEL HOUSING LINER "Installing"
- Fit wheels.
> 440519 Removing and installing wheel - "INSTALLING "
- Install right cross panel.
> WM 508119 REMOVING AND INSTALLING CROSS PANEL "Installing"
- Fit torque support.
> 103719 Removing and installing torque support - "INSTALLING "
- Fit design cover on the throttle valve.
>WM, 108319 REMOVING AND INSTALLING ENGINE COVER (DESIGN COVER) "Installing"
- Connect the battery.
- Fill the air conditioning system.
- Check engine-oil level.
- Bleed the cooling system.
> 193817 Draining and filling coolant (includes bleeding) - "FILLING "
- Bleed the power steering.
- Bleed the PDCC system if necessary.
- Check ATF level and top up if necessary.
- Move bonnet out of service position.
- Fit engine compartment trim panels.
- Perform suspension alignment.
- The high-pressure adaptation must be reset when replacing the engine.
- Read out DME fault memory and compare with the log you printed prior to removal.