Installing display and operator control unit (PCM 2)
WARNING: This page does not describe the selected car, but rather 7 other vehicles, including the 2005 Porsche 911, 2004 Porsche 911, 2003 Porsche 911, 2002 Porsche 911, and 2001 Porsche 911. However, it is still accessible from the selected car via links, so may be relevant.
NOTE:
- If a new PCM is installed, the navigation module from the old PCM is removed and installed in the new PCM.
- If the old PCM is installed again, start at step 6.
- Before the new PCM is installed, release and unplug the protective plug -A- for the optical waveguide.
- Unclip the cover on the new and old PCM.
- Lever out the navigation module carefully using a screwdriver on the removed PCM.
- Push navigation module into the PCM to be installed.
- Position the cover and clip it in.
- Connect the electrical plug connections of the display and operator control unit in the order -D, B, A- and the antenna plug -A, E, F- , until the plug engages audibly.
- Check if the locking tabs on the PCM protrude -arrow-
, and if so, open the locking with an Allen wrench.
NOTE: Before the PCM is inserted into the installation slot, it must be ensured that the electrical lines are not squeezed and damaged by the PCM.
- Push the PCM into the installation slot until the locking elements on the PCM housing engage.
- Plug in the electrical plug connections on the switch cover.
- Mount the switch cover and press in until it clicks into place.
NOTE: After installation of a new display and operator control unit, the system must be activated with the Porsche System Tester!
- Connect and switch on the Porsche System Tester 2.